TRIM SET,CONTROL VALVE,TYPE QO725,VITON

Material 4100043783 · TRIM SET · Plant 1000

ALong-leadReorderNormalBelow reorder point
Material
4100043783
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
203 d · P80 236 d
Unit price
Rp 33.4M

Recommendation

  • 1.Forecast 1.6 SET/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~203 days; expected demand during lead time 0.9.
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.On hand 3 + on order 0 is at or below the reorder point: order 3 now.
  • 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
3 SET
Rp 100.2M · order by 01 Oct 2026
Expected arrival ≈ 203 days
Long-leadSingle source
On hand / on order
3 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.5%
stockout risk now 3%
Unit price
Rp 33.4M
PO history
ML early warning: 15% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 167 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1454
PRESSURE CONTROL VALVE
A100.08
PX_FCV-1753
BY PASS LINE
B100.11
PX_TCV-734A
TEMPERATURE CONTROL VALVE
C100.12

Lead time and procurement

Lead time 203 ± 83 days (PO history + category, 1 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
29 Jul 2025PR01
Import / long-lead
2Rp 33.4M28 Jun 2026334 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
17 Apr 20262201000022069Corrective
25 Dec 20251201000030056Corrective
24 Dec 20251201000030056Corrective