TRIM SET,CONTROL VALVE,TYPE LZ113,MONEL

Material 4100043903 · TRIM SET · Plant 1000

CReducePotentially obsolete
Material
4100043903
Category
TRIM SET
Base unit
SET
MRP type
Stock Item
Criticality
C (0 of 1 FuncLocs A/B)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
160 d · P80 236 d
Unit price
Rp 45.5M

Recommendation

  • 1.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~160 days; expected demand during lead time 0.0.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 12 exceeds the level to keep (0) by 12.
Convert to Non StockSingle sourceOpen PO
On hand / on order
12 / 2
next delivery 25 Feb 2027
Today Min / Max
10 / 20
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 45.5M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 100,970/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~75 days.

Installed on 1 functional locations

0 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-723
PRESSURE CONTROL VALVE
C100.08

Lead time and procurement

Lead time 160 ± 83 days (PO history + category, 1 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
15 Sept 2026PR06
Regular replenishment
2Rp 45.5M25 Feb 2027
open
163 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.