TRIM SET,CONTROL VALVE,MODEL ZR45,VITON
Material 4100044738 · TRIM SET · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100044738
- Category
- TRIM SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- SURYA ENERGI JAYA PT
- Lead time
- 192 d · P80 236 d
- Unit price
- Rp 23.0M
Recommendation
- 1.Forecast 0.7 SET/year: 0.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~192 days; expected demand during lead time 0.4.
- 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.On hand 0 + on order 2 is at or below the reorder point: order 4 now.
- 5.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 92.0M · order by 01 Oct 2026
Expected arrival ≈ 192 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 14 May 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.2%
stockout risk now 12%
Unit price
Rp 23.0M
PO history
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 284 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 393.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.
Installed on 2 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1052 CONTROL VALVE | A | 2 | 0 | 0.11 |
| PX_TCV-1375 VD-708 TEMP CONTROL | B | 4 | 0 | 0.12 |
Lead time and procurement
Lead time 192 ± 83 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 23 Jun 2026 | PR05 Project / turnaround | 2 | Rp 22.9M | 14 May 2027 open | 325 d |
| 20 Jul 2025 | PR06 Regular replenishment | 2 | Rp 23.1M | 24 Dec 2025 | 157 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 21 Dec 2025 | 2 | 201000005653 | Corrective |
| 21 Dec 2025 | 1 | 201000005653 | Corrective |