Sparely
DU

TRIM SET,CONTROL VALVE,SIZE IR759,PTFE

Material 4100044858 · TRIM SET · Plant 1000

ALong-leadMonitorStockout
Material
4100044858
Category
TRIM SET
Base unit
SET
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
LANGIT MESINDO GLOBAL PT
Lead time
163 d · P80 236 d
Unit price
Rp 98.8M

Recommendation

  • 1.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~163 days; expected demand during lead time 0.2.
  • 3.A 98.2% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 236 days and the fastest seen in its category 75 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
0 / 2
next delivery 14 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.2%
stockout risk now 0%
Unit price
Rp 98.8M
PO history
ML early warning: 7% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 325 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 722.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~75 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1887C
BY PASS DUCT
A120.94
PX_FCV-524B
CONTROL VALVE
B100.11

Lead time and procurement

Lead time 163 ± 83 days (PO history + category, 2 PO lines) · on-time 37%

PR dateTypeQtyUnit priceDeliveryLead time
31 May 2026PR06
Regular replenishment
2Rp 101.6M14 Nov 2026
open
167 d
22 Jun 2025PR06
Regular replenishment
2Rp 96.0M09 Dec 2025170 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Jun 2026MediumPX_PCV-1887CInstall cover plate for MCP cracking
16 Jul 2025MediumPX_PCV-1887CPCV-1887C stuck

Recent goods issues

Posting dateQtyOrderOrder type
10 Nov 20251201000006937Corrective