PACKING SET,VALVE,MODEL FN612,NBR
Material 4100045035 · PACKING SET · Plant 1000
ASafety-criticalLong-leadMonitorHealthy
- Material
- 4100045035
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (83 of 149 FuncLocs A/B, 30 safety/shutdown valve)
- Supplier
- BERKAH REFRAKTORI PRATAMA PT
- Lead time
- 79 d · P80 96 d
- Unit price
- Rp 2.7M
Recommendation
- 1.Safety-critical element: installed on 30 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 29 SET/year: 25 unplanned (recency-weighted compound poisson (own history)) + 4.3 from the maintenance plan.
- 3.Lead time ~79 days; expected demand during lead time 7.5 (incl. 2.1 planned).
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 22, order up to 35.
- 5.Long lead time: 80% of deliveries took up to 96 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 149 FuncLoc(s), 83 of them criticality A/B.
- 7.ML early warning: 98% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningConvert to Stock ItemLast turnaround used 3Single sourceAbnormal consumptionOpen POPlanned demand in lead time
On hand / on order
3 / 73
next delivery 05 Dec 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
22
safety stock 15
Rec. Max
35
order qty 13
Service level
99.9%
stockout risk now 0%
Unit price
Rp 2.7M
PO history
ML early warning: 98% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 32 days ago, 16 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 4 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (3 units) excluded from the baseline.
Demand pattern Intermittent · 30 issue days · 3 abnormal issue(s) capped · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 13.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 149 functional locations
83 with criticality A/B · 178 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-168 PP-769B OUTLET FLOW | A | 1 | 5 | 1.82 |
| PX_LCV-1022A LEVEL CONTROL VALVE | A | 1 | 4 | 1.40 |
| PX_PCV-1960 PRESSURE CONTROL VALVE | A | 1 | 4 | 0.94 |
| PX_FCV-1272 CONTROL VALVE | A | 1 | 3 | 1.39 |
| PX_TCV-377C TEMPERATURE CONTROL VALVE | A | 1 | 3 | 0.98 |
| PX_FCV-1315A BY PASS LINE | A | 1 | 2 | 0.54 |
| PX_FCV-421A HE-1996B OUTLET FLOW | A | 1 | 2 | 0.96 |
| PX_PCV-1570 HE-846B PRESSURE CONTROL | A | 1 | 2 | 0.51 |
| PX_SDV-1940B ON-OFF VALVE | A | 1 | 2 | 0.06 |
| PX_TCV-533 TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.55 |
| PX_TCV-868 TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.55 |
| PY_FCV-1903 BFW FLOW CONTROL | A | 1 | 2 | 0.54 |
Lead time and procurement
Lead time 79 ± 47 days (PO history, 24 PO lines) · on-time 43%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 07 Sept 2026 | PR03 Regular replenishment | 31 | Rp 2.9M | 13 Dec 2026 open | 97 d |
| 30 Aug 2026 | PR10 Other | 12 | Rp 2.9M | 01 Apr 2027 open | 214 d |
| 24 Aug 2026 | PR03 Regular replenishment | 30 | Rp 2.7M | 05 Dec 2026 open | 103 d |
| 05 Jun 2026 | PR06 Regular replenishment | 15 | Rp 2.8M | 13 Jul 2026 | 38 d |
| 08 Feb 2026 | PR03 Regular replenishment | 19 | Rp 2.9M | 14 Mar 2026 | 34 d |
| 30 Jan 2026 | PR06 Regular replenishment | 30 | Rp 2.8M | 26 Apr 2026 | 86 d |
| 26 Dec 2025 | PR03 Regular replenishment | 19 | Rp 2.8M | 26 Mar 2026 | 90 d |
| 19 Dec 2025 | PR03 Regular replenishment | 27 | Rp 2.9M | 01 Feb 2026 | 44 d |
| 04 Dec 2025 | PR06 Regular replenishment | 29 | Rp 2.7M | 14 Jan 2026 | 41 d |
| 03 Dec 2025 | PR05 Project / turnaround | 24 | Rp 2.7M | 27 Apr 2026 | 145 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_TCV-1974 | Final Element Overhaul; CV | 0.72 |
| 01 Dec 2026 | PX_TCV-1173 | Final Element Overhaul; CV | 0.72 |
| 04 Dec 2026 | PX_FCV-168 | Final Element Overhaul; Control Valve | 0.72 |
| 19 Feb 2027 | PX_PCV-1400B | Final Element Overhaul; Control Valve | 2.15 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Sept 2026 | Medium | PX_FCV-168 | FCV-168 stuck |
| 17 Sept 2026 | Medium | PX_TCV-1851 | Install scaffolding at TCV-1851 |
| 13 Sept 2026 | Medium | PX_FCV-257B | Overhaul FCV-257B |
| 28 Aug 2026 | Low | PX_LCV-256 | LCV-256; valve hunting |
| 24 Aug 2026 | Medium | PX_TCV-998 | TCV-998 passing |
| 23 Aug 2026 | Medium | PX_FCV-257B | Overhaul FCV-257B |
| 12 Aug 2026 | Low | PX_LCV-1022A | Leak from packing |
| 05 Aug 2026 | Medium | PX_TCV-998 | Leak from packing |
| 02 Aug 2026 | Medium | PX_TCV-998 | [MSI-B-26-EHU-261] Permanent repair |
| 29 Jul 2026 | Medium | PX_LCV-1252 | LCV-1252 passing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Aug 2026 | 1 | 201000018854 | Corrective |
| 10 Aug 2026 | 1 | 201000016696 | Corrective |
| 06 Jun 2026 | 1 | 201000003941 | Corrective |
| 18 Feb 2026 | 1 | 201000037224 | Corrective |
| 28 Jan 2026 | 2 | 201000016979 | Corrective |
| 28 Jan 2026 | 1 | 201000016979 | Corrective |
| 21 Jan 2026 | 2 | 201000034532 | Corrective |
| 03 Jan 2026 | 1 | 201000020947 | Corrective |
| 02 Jan 2026 | 1 | 201000026947 | Corrective |
| 30 Dec 2025 | 1 | 201000034666 | Corrective |
| 29 Dec 2025 | 1 | 201000020183 | Corrective |
| 29 Dec 2025 | 1 | 201000034666 | Corrective |
| 28 Dec 2025 | 2 | 201000020183 | Corrective |
| 27 Dec 2025 | 2 | 201000026972 | Corrective |
| 27 Dec 2025 | 1 | 203000001878 | Turnaround |