PACKING SET,VALVE,MODEL YQ525,SS304
Material 4100045046 · PACKING SET · Plant 1000
ASafety-criticalLong-leadReduceExcess
- Material
- 4100045046
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (53 of 97 FuncLocs A/B, 22 safety/shutdown valve)
- Supplier
- BERKAH REFRAKTORI PRATAMA PT
- Lead time
- 125 d · P80 156 d
- Unit price
- Rp 5.3M
Recommendation
- 1.Safety-critical element: installed on 22 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 19 SET/year: 19 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~125 days; expected demand during lead time 6.6.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 22, order up to 30.
- 5.Stock 60 exceeds the level to keep (30) by 30.
- 6.Long lead time: 80% of deliveries took up to 156 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 97 FuncLoc(s), 53 of them criticality A/B.
- 8.ML early warning: 99% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningSingle sourceOpen PO
On hand / on order
60 / 83
next delivery 03 Oct 2026
Today Min / Max
31 / 74
static parameters in BoM
Rec. Min (reorder point)
22
safety stock 16
Rec. Max
30
order qty 8
Service level
99.9%
stockout risk now 0%
Unit price
Rp 5.3M
PO history
ML early warning: 99% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 8 issue days in the last 180 days, last issue 11 days ago, 11 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 8 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Smooth · 24 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 13.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 97 functional locations
53 with criticality A/B · 124 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-235B VD-719 OUTLET FLOW | A | 1 | 3 | 0.96 |
| PX_LCV-1811A HE-1121A LEVEL CONTROL | A | 3 | 3 | 0.97 |
| PX_FCV-1655A HE-1843C OUTLET FLOW | A | 1 | 2 | 0.54 |
| PX_MOV-846 MOTOR OPERATED GATE VALVE | A | 1 | 2 | 0.48 |
| PX_PCV-143A HE-1596B PRESSURE CONTROL | A | 1 | 1 | 0.08 |
| PX_PCV-629 PRESSURE CONTROL VALVE | A | 1 | 1 | 0.08 |
| PX_TCV-1322 PP-743D TEMP CONTROL | A | 1 | 1 | 0.12 |
| PY_SDV-1799A ON-OFF VALVE | A | 1 | 1 | 0.06 |
| PX_FCV-1088 BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_FCV-1152 RECYCLE ETHANE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_FCV-1647 KC-636C OUTLET FLOW | A | 2 | 0 | 0.11 |
| PX_FCV-1793 BY PASS LINE | A | 2 | 0 | 0.11 |
Lead time and procurement
Lead time 125 ± 73 days (PO history, 12 PO lines) · on-time 43%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 17 Sept 2026 | PR03 Regular replenishment | 12 | Rp 5.5M | 06 Jan 2027 open | 111 d |
| 19 Aug 2026 | PR03 Regular replenishment | 12 | Rp 5.2M | 15 Nov 2026 open | 88 d |
| 23 Jun 2026 | PR06 Regular replenishment | 12 | Rp 5.2M | 25 Sept 2026 | 94 d |
| 19 Jun 2026 | PR03 Regular replenishment | 12 | Rp 5.1M | 05 Jul 2027 open | 381 d |
| 15 Jun 2026 | PR03 Regular replenishment | 6 | Rp 5.2M | 03 Oct 2026 open | 110 d |
| 13 Jun 2026 | PR06 Regular replenishment | 5 | Rp 5.2M | 18 Oct 2026 open | 127 d |
| 13 Jun 2026 | PR03 Regular replenishment | 7 | Rp 5.4M | 15 Oct 2026 open | 124 d |
| 26 May 2026 | PR05 Project / turnaround | 15 | Rp 5.4M | 29 Dec 2026 open | 217 d |
| 26 Dec 2025 | PR05 Project / turnaround | 14 | Rp 5.2M | 04 Dec 2026 open | 343 d |
| 16 Dec 2025 | PR06 Regular replenishment | 6 | Rp 5.3M | 08 Feb 2026 | 54 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Sept 2026 | Medium | PX_LCV-326A | Leak from packing |
| 13 Sept 2026 | High | PX_TCV-771 | TCV-771 passing |
| 26 Aug 2026 | Medium | PX_TCV-899A | Replace lamp as per PM finding |
| 24 Aug 2026 | Medium | PX_MOV-846 | MOV-846 torque switch trip |
| 19 Aug 2026 | Medium | PX_FCV-235B | FCV-235B; valve hunting |
| 16 Aug 2026 | Low | PX_TCV-899A | Replace lamp as per PM finding |
| 11 Aug 2026 | Medium | PX_FCV-870 | [MSI-B-26-FHG-172/M] Replace line |
| 08 Aug 2026 | Medium | PX_SDV-459B | Leak from packing |
| 01 Aug 2026 | Low | PX_FCV-395 | FCV-395; valve hunting |
| 12 Jul 2026 | Medium | PX_TCV-1369 | Install cover plate for MCP cracking |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 20 Sept 2026 | 1 | 201000006305 | Corrective |
| 18 Sept 2026 | 1 | 201000030125 | Corrective |
| 27 Jul 2026 | 1 | 201000009720 | Corrective |
| 05 Jul 2026 | 1 | 201000016715 | Corrective |
| 16 Jun 2026 | 1 | 201000006665 | Corrective |
| 03 Jun 2026 | 1 | 201000037251 | Corrective |
| 02 Jun 2026 | 1 | 201000037251 | Corrective |
| 10 Apr 2026 | 1 | 201000034612 | Corrective |
| 20 Mar 2026 | 1 | 201000022759 | Corrective |
| 04 Mar 2026 | 1 | 201000028870 | Corrective |
| 10 Feb 2026 | 1 | 201000033056 | Corrective |
| 20 Jan 2026 | 1 | 201000026873 | Corrective |
| 08 Jan 2026 | 1 | 201000039284 | Corrective |
| 13 Dec 2025 | 1 | 201000021799 | Corrective |
| 08 Dec 2025 | 1 | 201000028486 | Corrective |