PACKING SET,VALVE,SIZE XM13,PTFE
Material 4100045149 · PACKING SET · Plant 1000
ASafety-criticalReorderCriticalStockout
- Material
- 4100045149
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (14 of 26 FuncLocs A/B, 3 safety/shutdown valve)
- Supplier
- SURYA ENERGI JAYA PT
- Lead time
- 62 d · P80 51 d
- Unit price
- Rp 4.5M
Recommendation
- 1.Safety-critical element: installed on 3 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 7.5 SET/year: 7.5 unplanned (recency-weighted compound poisson (own history)).
- 3.Lead time ~62 days; expected demand during lead time 1.3.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 8, order up to 13.
- 5.On hand 0 + on order 0 is at or below the reorder point: order 13 now.
- 6.Installed on 26 FuncLoc(s), 14 of them criticality A/B.
- 7.ML early warning: 56% probability of demand in the next 90 days.
Proposed purchase requisition
13 SET
Rp 59.1M · order by 01 Oct 2026
Expected arrival ≈ 62 days
Safety-critical (SCE)ML early warningConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
8
safety stock 7
Rec. Max
13
order qty 5
Service level
100.0%
stockout risk now 58%
Unit price
Rp 4.5M
PO history
ML early warning: 56% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 110 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 9 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 4.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 26 functional locations
14 with criticality A/B · 28 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1444A BY PASS LINE | A | 1 | 5 | 2.25 |
| PX_FCV-1315A BY PASS LINE | A | 1 | 2 | 0.54 |
| PX_SDV-289 C4 PRODUCT ISOLATION | A | 1 | 2 | 0.48 |
| PX_FCV-556A CONTROL VALVE | A | 1 | 1 | 0.11 |
| PX_LCV-610 LEVEL CONTROL VALVE | A | 1 | 1 | 0.12 |
| PX_FCV-1647 KC-636C OUTLET FLOW | A | 1 | 0 | 0.11 |
| PX_FCV-907A BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_PCV-1397 BY PASS DUCT | A | 1 | 0 | 0.08 |
| PX_TCV-998 PP-1470A TEMP CONTROL | B | 1 | 4 | 1.83 |
| PX_LCV-589B PP-389 LEVEL CONTROL | B | 1 | 2 | 0.55 |
| PX_FCV-1853 VD-1252 OUTLET FLOW | B | 1 | 0 | 0.11 |
| PX_FCV-277D PROPYLENE FLOW CONTROL | B | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 62 ± 29 days (PO history, 4 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 29 Jan 2026 | PR06 Regular replenishment | 5 | Rp 4.7M | 27 Feb 2026 | 29 d |
| 09 Oct 2025 | PR06 Regular replenishment | 6 | Rp 4.5M | 12 Nov 2025 | 34 d |
| 24 Sept 2025 | PR06 Regular replenishment | 6 | Rp 4.6M | 12 Nov 2025 | 49 d |
| 28 Jun 2025 | PR06 Regular replenishment | 4 | Rp 4.5M | 22 Aug 2025 | 55 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 24 Aug 2026 | Medium | PX_TCV-998 | TCV-998 passing |
| 05 Aug 2026 | Medium | PX_TCV-998 | Leak from packing |
| 02 Aug 2026 | Medium | PX_TCV-998 | [MSI-B-26-EHU-261] Permanent repair |
| 09 Jun 2026 | Medium | PX_FCV-1967 | FCV-1967 passing |
| 30 May 2026 | Low | PX_LCV-589B | LCV-589B stuck |
| 06 May 2026 | Low | PX_FCV-1444A | FCV-1444A passing |
| 15 Apr 2026 | Medium | PX_FCV-1444A | [MSI-B-26-NLB-110] Permanent repair |
| 12 Apr 2026 | Medium | PX_FCV-1967 | FCV-1967; IA leak from regulator |
| 19 Mar 2026 | Low | PX_FCV-1315A | FCV-1315A; IA leak from regulator |
| 18 Mar 2026 | Medium | PX_FCV-381 | FCV-381; IA leak from regulator |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Jun 2026 | 1 | 206000013860 | Other maintenance |
| 17 May 2026 | 1 | 201000026522 | Corrective |
| 10 Jan 2026 | 1 | 201000024092 | Corrective |
| 24 Dec 2025 | 2 | 201000010275 | Corrective |
| 23 Dec 2025 | 1 | 201000010275 | Corrective |
| 05 Dec 2025 | 1 | 201000029239 | Corrective |
| 23 Sept 2025 | 2 | 201000009723 | Corrective |
| 30 Aug 2025 | 3 | 201000031462 | Corrective |
| 02 Jul 2025 | 1 | 201000026142 | Corrective |