PACKING SET,VALVE,SIZE NY148,CS

Material 4100045160 · PACKING SET · Plant 1000

ASafety-criticalLong-leadMonitorSlow-moving
Material
4100045160
Category
PACKING SET
Base unit
SET
MRP type
Non Stock
Criticality
A (10 of 23 FuncLocs A/B, 6 safety/shutdown valve)
Supplier
SINAR SEJAHTERA LESTARI PT
Lead time
100 d · P80 112 d
Unit price
Rp 11.6M

Recommendation

  • 1.Safety-critical element: installed on 6 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 6.3 SET/year: 4.8 unplanned (recency-weighted compound poisson (own history)) + 1.4 from the maintenance plan.
  • 3.Lead time ~100 days; expected demand during lead time 2.8 (incl. 1.4 planned).
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 9, order up to 12.
  • 5.Long lead time: 80% of deliveries took up to 112 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 23 FuncLoc(s), 10 of them criticality A/B.
  • 7.ML early warning: 75% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningConvert to Stock ItemSingle sourceOpen POPlanned demand in lead time
On hand / on order
6 / 5
next delivery 05 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
9
safety stock 7
Rec. Max
12
order qty 3
Service level
100.0%
stockout risk now 0%
Unit price
Rp 11.6M
PO history
ML early warning: 75% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 191 days ago, 3 failure notifications on its equipment in 90 days, 2 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 23 functional locations

10 with criticality A/B · 28 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1343
CONTROL VALVE
A100.11
PX_FCV-933A
RECYCLE ETHANE FLOW CONTROL
A200.11
PX_MOV-873D
MOTOR OPERATED GATE VALVE
A400.06
PX_PCV-616C
BY PASS DUCT
A100.08
PX_PCV-935
KC-582B PRESSURE CONTROL
A100.08
PX_SDV-1238
PP-1269A SHUTDOWN VALVE
A200.06
PX_LCV-791
PP-818 LEVEL CONTROL
B100.12
PX_LCV-896A
LEVEL CONTROL VALVE
B100.12
PX_SDV-1405
PP-1892C SHUTDOWN VALVE
B100.06
PY_FCV-476
CONTROL VALVE
B100.11
PX_FCV-1447
ETHYLENE FLOW CONTROL
C131.39
PX_TCV-745
PP-1161 TEMP CONTROL
C130.98

Lead time and procurement

Lead time 100 ± 54 days (PO history, 7 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
12 Aug 2026PR06
Regular replenishment
4Rp 11.9M03 Dec 2026
open
113 d
20 Jul 2026PR03
Regular replenishment
1Rp 11.4M05 Nov 2026
open
108 d
11 Jun 2026PR03
Regular replenishment
4Rp 11.6M22 Aug 202672 d
24 Feb 2026PR06
Regular replenishment
1Rp 11.4M23 Apr 202658 d
08 Nov 2025PR06
Regular replenishment
2Rp 12.0M17 Jun 2026221 d
30 Jul 2025PR06
Regular replenishment
4Rp 11.5M08 Oct 202570 d
06 May 2025PR06
Regular replenishment
2Rp 12.3M12 Aug 202598 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_SDV-1751Final Element Overhaul; ONOFFV0.72
17 Dec 2026PX_FCV-1447Final Element Overhaul; CV0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
08 Sept 2026LowPX_TCV-745TCV-745; IA leak from regulator
19 Aug 2026MediumPX_FCV-1447FCV-1447; IA leak from regulator
27 Jul 2026MediumPX_TCV-745Install cover plate for MCP cracking
20 Jun 2026LowPX_SDV-683BCheck SDV-683B.ok
03 Dec 2025MediumPX_SDV-1568A[MSI-B-25-UEB-389] Permanent repair
30 Nov 2025HighPX_FCV-1447[MSI-B-25-JDZ-246] Permanent repair
05 Nov 2025MediumPY_LCV-1154ALCV-1154A passing
23 Aug 2025LowPY_LCV-1154ALCV-1154A; valve hunting
22 Jul 2025LowPX_TCV-745Install scaffolding at TCV-745
14 Jun 2025MediumPX_FCV-1447FCV-1447 passing

Recent goods issues

Posting dateQtyOrderOrder type
24 Mar 20262201000014641Corrective
23 Mar 20262201000014641Corrective
13 Dec 20252201000001323Corrective
01 Dec 20251201000028524Corrective
28 Oct 20251201000024737Corrective
26 Sept 20251201000032684Corrective