PACKING SET,VALVE,SIZE YW314,SS316
Material 4100045194 · PACKING SET · Plant 1000
ASafety-criticalLong-leadReorderNormalSlow-moving
- Material
- 4100045194
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (11 of 19 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- SURYA PERKASA SENTOSA PT
- Lead time
- 92 d · P80 145 d
- Unit price
- Rp 1.4M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 3.2 SET/year: 3.2 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~92 days; expected demand during lead time 0.8.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 10.
- 5.On hand 4 + on order 1 is at or below the reorder point: order 5 now.
- 6.Long lead time: 80% of deliveries took up to 145 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 19 FuncLoc(s), 11 of them criticality A/B.
- 8.ML early warning: 39% probability of demand in the next 90 days.
Proposed purchase requisition
5 SET
Rp 7.2M · order by 01 Oct 2026
Expected arrival ≈ 92 days
Safety-critical (SCE)Long-leadML early warningSingle sourceOpen PO
On hand / on order
4 / 1
next delivery 13 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 6
Rec. Max
10
order qty 4
Service level
99.9%
stockout risk now 1%
Unit price
Rp 1.4M
PO history
ML early warning: 39% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 255 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 19 functional locations
11 with criticality A/B · 27 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1052 CONTROL VALVE | A | 4 | 0 | 0.11 |
| PX_FCV-1156C PP-1323A OUTLET FLOW | A | 1 | 0 | 0.11 |
| PX_FCV-1181 CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-1326 BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_LCV-1703 PP-1325 LEVEL CONTROL | A | 3 | 0 | 0.12 |
| PX_PCV-1453 PRESSURE CONTROL VALVE | A | 1 | 0 | 0.08 |
| PX_PCV-392A BY PASS DUCT | A | 1 | 0 | 0.08 |
| PX_TCV-233 TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PY_TCV-647A TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_SDV-130A PP-1471A SHUTDOWN VALVE | B | 1 | 4 | 0.91 |
| PX_PCV-204 PP-588 PRESSURE CONTROL | B | 1 | 0 | 0.08 |
| PX_FCV-1967 CONTROL VALVE | C | 1 | 6 | 2.25 |
Lead time and procurement
Lead time 92 ± 50 days (PO history + category, 1 PO lines) · on-time 25%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 03 Jul 2026 | PR03 Regular replenishment | 1 | Rp 1.4M | 13 Oct 2026 open | 102 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 09 Jun 2026 | Medium | PX_FCV-1967 | FCV-1967 passing |
| 12 Apr 2026 | Medium | PX_FCV-1967 | FCV-1967; IA leak from regulator |
| 08 Apr 2026 | Medium | PX_SDV-130A | Check SDV-130A.ok |
| 21 Jan 2026 | Medium | PX_FCV-1967 | FCV-1967; IA leak from regulator |
| 11 Jan 2026 | Medium | PX_FCV-1967 | FCV-1967; small leak at packing |
| 01 Nov 2025 | Low | PX_FCV-1967 | Install scaffolding at FCV-1967 |
| 24 Oct 2025 | Low | PX_SDV-130A | Install scaffolding at SDV-130A |
| 17 Aug 2025 | Medium | PX_SDV-130A | SDV-130A solenoid burnt |
| 23 Jul 2025 | Medium | PX_FCV-1967 | FCV-1967 passing |
| 10 May 2025 | Medium | PX_SDV-130A | Install scaffolding at SDV-130A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 19 Jan 2026 | 2 | 201000009432 | Corrective |