PACKING SET,VALVE,MODEL FZ462,SS304
Material 4100045253 · PACKING SET · Plant 1000
ASafety-criticalLong-leadReorderNormalBelow reorder point
- Material
- 4100045253
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (9 of 14 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 132 d · P80 210 d
- Unit price
- Rp 3.7M
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 7.0 SET/year: 4.8 unplanned (recency-weighted compound poisson (own history)) + 2.1 from the maintenance plan.
- 3.Lead time ~132 days; expected demand during lead time 3.2 (incl. 1.4 planned).
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 10, order up to 16.
- 5.On hand 4 + on order 4 is at or below the reorder point: order 8 now.
- 6.Long lead time: 80% of deliveries took up to 210 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 14 FuncLoc(s), 9 of them criticality A/B.
- 8.ML early warning: 45% probability of demand in the next 90 days.
Proposed purchase requisition
8 SET
Rp 29.4M · order by 01 Oct 2026
Expected arrival ≈ 132 days
Safety-critical (SCE)Long-leadML early warningSingle sourceOpen POPlanned demand in lead time
On hand / on order
4 / 4
next delivery 16 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
10
safety stock 7
Rec. Max
16
order qty 6
Service level
100.0%
stockout risk now 1%
Unit price
Rp 3.7M
PO history
ML early warning: 45% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 86 days ago, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 6 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 14 functional locations
9 with criticality A/B · 18 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1543 HE-1524B PRESSURE CONTROL | A | 2 | 2 | 0.51 |
| PX_FCV-1116 CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_LCV-1741 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_SDV-1089B SLOP OIL ISOLATION | A | 1 | 0 | 0.06 |
| PX_SDV-848B VD-664B SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PX_TCV-1224 KC-369B TEMP CONTROL | B | 1 | 7 | 2.26 |
| PX_LCV-1619A LEVEL CONTROL VALVE | B | 1 | 0 | 0.12 |
| PX_PCV-805 BY PASS DUCT | B | 4 | 0 | 0.08 |
| PX_TCV-254 TEMPERATURE CONTROL VALVE | B | 1 | 0 | 0.12 |
| PX_FCV-1193 CONTROL VALVE | C | 1 | 0 | 0.11 |
| PX_LCV-1074A HE-354D LEVEL CONTROL | C | 1 | 0 | 0.12 |
| PX_TCV-807A CL-1871 TEMP CONTROL | C | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 132 ± 73 days (PO history, 4 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 11 Sept 2026 | PR03 Regular replenishment | 2 | Rp 3.7M | 17 Feb 2027 open | 159 d |
| 02 Feb 2026 | PR06 Regular replenishment | 2 | Rp 3.7M | 16 Nov 2026 open | 287 d |
| 23 Oct 2025 | PR06 Regular replenishment | 4 | Rp 3.6M | 31 Dec 2025 | 69 d |
| 08 Oct 2025 | PR05 Project / turnaround | 3 | Rp 3.7M | 01 Mar 2026 | 144 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Oct 2026 | PX_PCV-1543 | Final Element Overhaul; CV | 1.43 |
| 01 Apr 2027 | PX_LCV-1074A | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Aug 2026 | Low | PX_TCV-1224 | Install scaffolding at TCV-1224 |
| 23 Jul 2026 | Medium | PX_TCV-1224 | TCV-1224 passing |
| 25 Jun 2026 | Medium | PX_TCV-1224 | TCV-1224; IA leak from regulator |
| 18 May 2026 | Medium | PX_TCV-1224 | TCV-1224; small leak at packing |
| 25 Dec 2025 | Medium | PX_TCV-1224 | Replace lamp as per PM finding |
| 31 Oct 2025 | High | PX_PCV-1543 | PCV-1543 passing |
| 25 Aug 2025 | Low | PX_TCV-1224 | Overhaul TCV-1224 |
| 10 May 2025 | Low | PX_PCV-1543 | PCV-1543; IA leak from regulator |
| 02 May 2025 | High | PX_TCV-1224 | Overhaul TCV-1224 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 07 Jul 2026 | 1 | 201000004880 | Corrective |
| 06 Jul 2026 | 2 | 201000004880 | Corrective |
| 09 Jan 2026 | 2 | 201000000591 | Corrective |
| 11 Dec 2025 | 1 | 201000010938 | Corrective |
| 12 Nov 2025 | 1 | 201000001935 | Corrective |
| 23 Aug 2025 | 1 | 201000030762 | Corrective |