PACKING SET,VALVE,SIZE VJ545,SS304

Material 4100045297 · PACKING SET · Plant 1000

ASafety-criticalReorderNormalBelow reorder point
Material
4100045297
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (5 of 8 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 3.8 SET/year: 3.8 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~88 days; expected demand during lead time 0.9.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 7, order up to 11.
  • 5.On hand 1 + on order 0 is at or below the reorder point: order 10 now.
  • 6.Installed on 8 FuncLoc(s), 5 of them criticality A/B.
Proposed purchase requisition
10 SET
Rp 38.4M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
7
safety stock 7
Rec. Max
11
order qty 4
Service level
100.0%
stockout risk now 42%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 23% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 13 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 8 functional locations

5 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1444A
BY PASS LINE
A152.25
PX_TCV-386
TEMPERATURE CONTROL VALVE
A130.98
PX_PCV-1011A
PRESSURE CONTROL VALVE
A100.08
PX_PCV-935
KC-582B PRESSURE CONTROL
A100.08
PY_FCV-178
PP-339C OUTLET FLOW
A200.11
PX_PCV-1614
BY PASS DUCT
C300.08
PX_PCV-1868A
PRESSURE CONTROL VALVE
S100.08
PX_SDV-151
ON-OFF VALVE
S100.06

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
19 Aug 2026MediumPX_TCV-386TCV-386; valve hunting
06 May 2026LowPX_FCV-1444AFCV-1444A passing
05 May 2026MediumPX_TCV-386Overhaul TCV-386
15 Apr 2026MediumPX_FCV-1444A[MSI-B-26-NLB-110] Permanent repair
12 Jan 2026MediumPX_FCV-1444AFCV-1444A; valve hunting
17 Dec 2025LowPX_FCV-1444AFCV-1444A; small leak at packing
01 Jun 2025MediumPX_FCV-1444APSM25/Overhaul FCV-1444A
29 May 2025MediumPX_TCV-386TCV-386 stuck

Recent goods issues

Posting dateQtyOrderOrder type
18 Sept 20262201000033583Corrective
17 May 20261201000026522Corrective
02 Jun 20252201000013661Corrective