PACKING SET,VALVE,SIZE HE334,GRAPHITE
Material 4100045342 · PACKING SET · Plant 1000
ASafety-criticalLong-leadReduceSlow-moving
- Material
- 4100045342
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Non Stock
- Criticality
- A (2 of 8 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- PERMATA INSTRUMEN INTERNASIONAL PT
- Lead time
- 99 d · P80 142 d
- Unit price
- Rp 2.7M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.6 SET/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~99 days; expected demand during lead time 0.4.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 7.
- 5.Stock 18 exceeds the level to keep (7) by 11.
- 6.Long lead time: 80% of deliveries took up to 142 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 8 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Long-leadConvert to Stock ItemSingle sourceOpen PO
On hand / on order
18 / 2
next delivery 25 Oct 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
7
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 2.7M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 235 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 857.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 8 functional locations
2 with criticality A/B · 8 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1256 PP-1570A TEMP CONTROL | A | 1 | 4 | 1.40 |
| PX_FCV-1733 SPENT CAUSTIC FLOW CONTROL | B | 1 | 0 | 0.11 |
| PX_FCV-129D BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_FCV-1797 CONTROL VALVE | C | 1 | 0 | 0.11 |
| PX_LCV-1384 HE-694C LEVEL CONTROL | C | 1 | 0 | 0.12 |
| PX_LCV-1594 LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_SDV-1535D ON-OFF VALVE | S | 1 | 0 | 0.06 |
| PY_PCV-885 BY PASS DUCT | S | 1 | 0 | 0.08 |
Lead time and procurement
Lead time 99 ± 57 days (PO history, 3 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 24 Apr 2026 | PR06 Regular replenishment | 2 | Rp 2.7M | 25 Oct 2026 open | 184 d |
| 14 Feb 2026 | PR06 Regular replenishment | 2 | Rp 2.6M | 05 May 2026 | 80 d |
| 07 Oct 2025 | PR06 Regular replenishment | 1 | Rp 2.7M | 12 Dec 2025 | 66 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Jul 2026 | Low | PX_TCV-1256 | TCV-1256; IA leak from regulator |
| 29 Jul 2026 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
| 16 Apr 2026 | Medium | PX_TCV-1256 | Replace lamp as per PM finding |
| 05 May 2025 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Feb 2026 | 2 | 201000004710 | Corrective |
| 14 Dec 2025 | 1 | 201000017345 | Corrective |