PACKING SET,VALVE,TYPE WL414,SS316
Material 4100045425 · PACKING SET · Plant 1000
ASafety-criticalReorderNormalSlow-moving
- Material
- 4100045425
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (4 of 10 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- No PO history
- Lead time
- 88 d · P80 145 d
- Unit price
- Rp 3.8M (est.)
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.3 SET/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~88 days; expected demand during lead time 0.3.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 5.On hand 1 + on order 0 is at or below the reorder point: order 5 now.
- 6.Installed on 10 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
5 SET
Rp 19.2M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 15%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 19% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 402 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 537.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 10 functional locations
4 with criticality A/B · 10 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1644 VD-981A OUTLET FLOW | A | 1 | 2 | 0.11 |
| PX_FCV-1514A RECYCLE ETHANE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_PCV-194 HE-1680D PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_LCV-1573B KC-843 LEVEL CONTROL | B | 1 | 1 | 0.12 |
| PX_LCV-1417A LEVEL CONTROL VALVE | C | 1 | 1 | 0.55 |
| PX_FCV-1259 CONTROL VALVE | C | 1 | 0 | 0.11 |
| PX_FCV-1377 BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_LCV-174 LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_LCV-725 LEVEL CONTROL VALVE | S | 1 | 1 | 0.55 |
| PX_SDV-842 HE-785C SHUTDOWN VALVE | S | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 17 Aug 2026 | Medium | PX_FCV-1644 | Install scaffolding at FCV-1644 |
| 22 Jun 2025 | Medium | PX_LCV-725 | Leak from packing |
| 14 Jun 2025 | Medium | PX_LCV-1417A | Replace lamp as per PM finding |
| 29 May 2025 | Low | PX_FCV-1644 | Leak from packing |
| 10 May 2025 | Medium | PX_LCV-1573B | Install scaffolding at LCV-1573B |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 25 Aug 2025 | 2 | 201000011450 | Corrective |