PACKING SET,VALVE,TYPE FE44,INCOLOY

Material 4100045431 · PACKING SET · Plant 1000

ASafety-criticalLong-leadReorderCriticalStockout
Material
4100045431
Category
PACKING SET
Base unit
SET
MRP type
Non Stock
Criticality
A (4 of 10 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
110 d · P80 166 d
Unit price
Rp 6.1M

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.5 SET/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~110 days; expected demand during lead time 0.5.
  • 4.A 99.6% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 5 now.
  • 6.Long lead time: 80% of deliveries took up to 166 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 10 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
5 SET
Rp 30.6M · order by 01 Oct 2026
Expected arrival ≈ 110 days
Safety-critical (SCE)Long-leadConvert to Stock ItemLast turnaround used 1Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.6%
stockout risk now 26%
Unit price
Rp 6.1M
PO history
ML early warning: 23% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 278 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 818.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 10 functional locations

4 with criticality A/B · 14 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1887C
BY PASS DUCT
A120.94
PX_LCV-1032
LEVEL CONTROL VALVE
A100.12
PX_PCV-1454
PRESSURE CONTROL VALVE
A100.08
PX_SDV-1526
CHARGE GAS ISOLATION
A100.06
PX_FCV-580A
HE-108B OUTLET FLOW
C100.11
PX_LCV-1043
KC-279C LEVEL CONTROL
C400.12
PX_LCV-1384
HE-694C LEVEL CONTROL
C100.12
PX_PCV-1135
PP-1811A PRESSURE CONTROL
C100.08
PX_LCV-725
LEVEL CONTROL VALVE
S110.55
PX_SDV-445
FUEL OIL ISOLATION
S210.48

Lead time and procurement

Lead time 110 ± 55 days (PO history, 4 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
17 Feb 2026PR06
Regular replenishment
1Rp 6.2M10 Jul 2026143 d
06 Nov 2025PR06
Regular replenishment
2Rp 6.3M12 Feb 202698 d
06 Oct 2025PR06
Regular replenishment
1Rp 6.1M12 Dec 202567 d
15 Aug 2025PR04
Regular (other)
2Rp 6.0M03 Mar 2026200 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Jun 2026MediumPX_PCV-1887CInstall cover plate for MCP cracking
16 Jul 2025MediumPX_PCV-1887CPCV-1887C stuck
15 Jul 2025HighPX_SDV-445SDV-445 limit switch faulty
22 Jun 2025MediumPX_LCV-725Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
27 Dec 20251201000014032Corrective
15 Dec 20251203000027801Turnaround
23 Jul 20252201000034933Corrective