Sparely
DU

PACKING SET,VALVE,SIZE QS820,VITON

Material 4100045475 · PACKING SET · Plant 1000

ASafety-criticalReduceNon-moving
Material
4100045475
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 5 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~88 days; expected demand during lead time 0.0.
  • 4.A 97.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 5.Stock 5 exceeds the level to keep (2) by 3.
  • 6.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
5 / 0
no open PO
Today Min / Max
4 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
97.9%
stockout risk now 0%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 72.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 5 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1958
PRESSURE CONTROL VALVE
A100.08
PX_SDV-1894
ON-OFF VALVE
B151.77
PX_FCV-746
BY PASS LINE
C100.11
PX_TCV-1253
VD-1641A TEMP CONTROL
C100.12
PX_PCV-1795
PRESSURE CONTROL VALVE
S100.08

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
13 Aug 2026HighPX_SDV-1894SDV-1894 limit switch faulty
17 Jul 2026MediumPX_SDV-1894SDV-1894 limit switch faulty
29 Jan 2026MediumPX_SDV-1894Replace lamp as per PM finding
14 Nov 2025MediumPX_SDV-1894SDV-1894 fail to close
13 May 2025MediumPX_SDV-1894Install scaffolding at SDV-1894

Recent goods issues

Never issued in the 17-month history.