PACKING SET,VALVE,MODEL IV777,NBR
Material 4100045507 · PACKING SET · Plant 1000
ASafety-criticalLong-leadReorderNormalBelow reorder point
- Material
- 4100045507
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (4 of 9 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- BERKAH REFRAKTORI PRATAMA PT
- Lead time
- 115 d · P80 190 d
- Unit price
- Rp 11.9M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 3.7 SET/year: 3.7 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~115 days; expected demand during lead time 1.2.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 8.
- 5.On hand 2 + on order 2 is at or below the reorder point: order 4 now.
- 6.Long lead time: 80% of deliveries took up to 190 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 7.Installed on 9 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 47.7M · order by 01 Oct 2026
Expected arrival ≈ 115 days
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 24 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
8
order qty 3
Service level
99.9%
stockout risk now 1%
Unit price
Rp 11.9M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 9 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 9 functional locations
4 with criticality A/B · 17 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1444A BY PASS LINE | A | 1 | 5 | 2.25 |
| PX_FCV-1448A HE-536 OUTLET FLOW | B | 1 | 1 | 0.11 |
| PX_FCV-256A BY PASS LINE | B | 2 | 0 | 0.11 |
| PX_LCV-386B PP-1598B LEVEL CONTROL | B | 2 | 0 | 0.12 |
| PX_FCV-1206 CONTROL VALVE | C | 1 | 0 | 0.11 |
| PX_TCV-124A TEMPERATURE CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_TCV-725 TEMPERATURE CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_FCV-1528A VD-1391A OUTLET FLOW | S | 4 | 0 | 0.11 |
| PX_SDV-1982 ON-OFF VALVE | S | 4 | 0 | 0.06 |
Lead time and procurement
Lead time 115 ± 68 days (PO history, 4 PO lines) · on-time 43%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 06 Jul 2026 | PR06 Regular replenishment | 1 | Rp 12.4M | 13 Sept 2026 | 69 d |
| 26 Mar 2026 | PR03 Regular replenishment | 2 | Rp 11.8M | 24 Nov 2026 open | 243 d |
| 19 Oct 2025 | PR06 Regular replenishment | 2 | Rp 12.0M | 05 Jan 2026 | 78 d |
| 09 Jun 2025 | PR03 Regular replenishment | 2 | Rp 11.5M | 10 Nov 2025 | 154 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 06 May 2026 | Low | PX_FCV-1444A | FCV-1444A passing |
| 15 Apr 2026 | Medium | PX_FCV-1444A | [MSI-B-26-NLB-110] Permanent repair |
| 12 Jan 2026 | Medium | PX_FCV-1444A | FCV-1444A; valve hunting |
| 17 Dec 2025 | Low | PX_FCV-1444A | FCV-1444A; small leak at packing |
| 01 Jun 2025 | Medium | PX_FCV-1444A | PSM25/Overhaul FCV-1444A |
| 07 May 2025 | Medium | PX_FCV-1448A | Overhaul FCV-1448A |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Sept 2026 | 1 | 204000002989 | Preventive |
| 09 Aug 2026 | 1 | 204000027173 | Preventive |
| 27 Jan 2026 | 1 | 201000032388 | Corrective |
| 09 Jan 2026 | 1 | 201000024572 | Corrective |
| 08 Jan 2026 | 1 | 201000024572 | Corrective |