PACKING SET,VALVE,MODEL IV777,NBR

Material 4100045507 · PACKING SET · Plant 1000

ASafety-criticalLong-leadReorderNormalBelow reorder point
Material
4100045507
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (4 of 9 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
BERKAH REFRAKTORI PRATAMA PT
Lead time
115 d · P80 190 d
Unit price
Rp 11.9M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 3.7 SET/year: 3.7 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~115 days; expected demand during lead time 1.2.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 8.
  • 5.On hand 2 + on order 2 is at or below the reorder point: order 4 now.
  • 6.Long lead time: 80% of deliveries took up to 190 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 7.Installed on 9 FuncLoc(s), 4 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 47.7M · order by 01 Oct 2026
Expected arrival ≈ 115 days
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
2 / 2
next delivery 24 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 4
Rec. Max
8
order qty 3
Service level
99.9%
stockout risk now 1%
Unit price
Rp 11.9M
PO history
ML early warning: 16% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 9 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 3.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 9 functional locations

4 with criticality A/B · 17 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1444A
BY PASS LINE
A152.25
PX_FCV-1448A
HE-536 OUTLET FLOW
B110.11
PX_FCV-256A
BY PASS LINE
B200.11
PX_LCV-386B
PP-1598B LEVEL CONTROL
B200.12
PX_FCV-1206
CONTROL VALVE
C100.11
PX_TCV-124A
TEMPERATURE CONTROL VALVE
C100.12
PX_TCV-725
TEMPERATURE CONTROL VALVE
C100.12
PX_FCV-1528A
VD-1391A OUTLET FLOW
S400.11
PX_SDV-1982
ON-OFF VALVE
S400.06

Lead time and procurement

Lead time 115 ± 68 days (PO history, 4 PO lines) · on-time 43%

PR dateTypeQtyUnit priceDeliveryLead time
06 Jul 2026PR06
Regular replenishment
1Rp 12.4M13 Sept 202669 d
26 Mar 2026PR03
Regular replenishment
2Rp 11.8M24 Nov 2026
open
243 d
19 Oct 2025PR06
Regular replenishment
2Rp 12.0M05 Jan 202678 d
09 Jun 2025PR03
Regular replenishment
2Rp 11.5M10 Nov 2025154 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
06 May 2026LowPX_FCV-1444AFCV-1444A passing
15 Apr 2026MediumPX_FCV-1444A[MSI-B-26-NLB-110] Permanent repair
12 Jan 2026MediumPX_FCV-1444AFCV-1444A; valve hunting
17 Dec 2025LowPX_FCV-1444AFCV-1444A; small leak at packing
01 Jun 2025MediumPX_FCV-1444APSM25/Overhaul FCV-1444A
07 May 2025MediumPX_FCV-1448AOverhaul FCV-1448A

Recent goods issues

Posting dateQtyOrderOrder type
22 Sept 20261204000002989Preventive
09 Aug 20261204000027173Preventive
27 Jan 20261201000032388Corrective
09 Jan 20261201000024572Corrective
08 Jan 20261201000024572Corrective