PACKING SET,VALVE,TYPE OP701,SS316

Material 4100045635 · PACKING SET · Plant 1000

ALong-leadMaintainHealthy
Material
4100045635
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (3 of 5 FuncLocs A/B)
Supplier
LANGIT SEJAHTERA PRATAMA PT
Lead time
112 d · P80 145 d
Unit price
Rp 1.4M

Recommendation

  • 1.Forecast 1.9 SET/year: 1.9 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~112 days; expected demand during lead time 0.6.
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Long lead time: 80% of deliveries took up to 145 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 5 FuncLoc(s), 3 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
5 / 1
next delivery 05 Dec 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.4M
PO history
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 117 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 5 functional locations

3 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_MOV-1649A
MOTOR OPERATED GATE VALVE
A131.34
PX_LCV-150
HE-492C LEVEL CONTROL
A100.12
PX_PCV-1453
PRESSURE CONTROL VALVE
A100.08
PX_FCV-739
CONTROL VALVE
C300.11
PX_PCV-1623D
HE-1982 PRESSURE CONTROL
S100.08

Lead time and procurement

Lead time 112 ± 50 days (PO history + category, 2 PO lines) · on-time 40%

PR dateTypeQtyUnit priceDeliveryLead time
08 May 2026PR01
Import / long-lead
1Rp 1.4M05 Dec 2026
open
211 d
10 Aug 2025PR03
Regular replenishment
2Rp 1.4M01 Nov 202583 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
22 Sept 2026EmergencyPX_MOV-1649AMOV-1649A torque switch trip
26 Aug 2026LowPX_MOV-1649AMOV-1649A torque switch trip
06 Aug 2025MediumPX_MOV-1649AReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
06 Jun 20261201000019897Corrective
05 Jun 20261201000019897Corrective
14 Jan 20261201000019532Corrective