Sparely
DU

PACKING SET,VALVE,MODEL DP213,SS316

Material 4100045836 · PACKING SET · Plant 1000

ASafety-criticalMonitorHealthy
Material
4100045836
Category
PACKING SET
Base unit
SET
MRP type
Non Stock
Criticality
A (3 of 4 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.3 SET/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~88 days; expected demand during lead time 0.3.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.Installed on 4 FuncLoc(s), 3 of them criticality A/B.
Safety-critical (SCE)Convert to Stock ItemLast turnaround used 1Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 2 issue days in the last 180 days, last issue 39 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (1 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 4 functional locations

3 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-691B
CONTROL VALVE
A120.54
PX_PCV-1496A
PP-821 PRESSURE CONTROL
A100.08
PX_SDV-1660
ON-OFF VALVE
A100.06
PX_TCV-727D
HE-1305 TEMP CONTROL
C100.12

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
13 Sept 2026MediumPX_FCV-691BFCV-691B; small leak at packing
28 May 2025MediumPX_FCV-691BReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
23 Aug 20261201000025267Corrective
08 Apr 20261201000017654Corrective
26 Dec 20251203000016277Turnaround