Sparely
DU

PACKING SET,VALVE,SIZE BI439,INCOLOY

Material 4100045896 · PACKING SET · Plant 1000

AMaintainCritical insurance spare
Material
4100045896
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Forecast 0.1 SET/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 2.Lead time ~88 days; expected demand during lead time 0.0.
  • 3.A 98.6% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 4.No issue in 17 months, but it protects critical equipment: keep it.
  • 5.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
2 / 6
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
98.6%
stockout risk now 0%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 49.4M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1272
CONTROL VALVE
A131.39
PX_PCV-655B
BY PASS DUCT
A110.08

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
25 Jun 2026HighPX_FCV-1272FCV-1272 stuck
27 Oct 2025EmergencyPX_FCV-1272Leak from packing
25 Jun 2025MediumPX_FCV-1272Replace lamp as per PM finding
08 May 2025MediumPX_PCV-655BPCV-655B; IA leak from regulator

Recent goods issues

Never issued in the 17-month history.