PACKING SET,VALVE,SIZE EG119,VITON

Material 4100045901 · PACKING SET · Plant 1000

ASafety-criticalReduceNon-moving
Material
4100045901
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (1 of 4 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.0 SET/year: 0.0 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~88 days; expected demand during lead time 0.0.
  • 4.A 99.7% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 2.
  • 5.Stock 35 exceeds the level to keep (2) by 33.
  • 6.Installed on 4 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
35 / 0
no open PO
Today Min / Max
2 / 4
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
2
order qty 2
Service level
99.7%
stockout risk now 0%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 11.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 4 functional locations

1 with criticality A/B · 7 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_SDV-1375
FLUSHING OIL ISOLATION
A400.06
PX_FCV-1193
CONTROL VALVE
C100.11
PX_LCV-1317A
VD-105C LEVEL CONTROL
C100.12
PX_SDV-869
ON-OFF VALVE
C100.06

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Never issued in the 17-month history.