PACKING SET,VALVE,SIZE FP49,A105

Material 4100045934 · PACKING SET · Plant 1000

ASafety-criticalReorderCriticalInsurance gap
Material
4100045934
Category
PACKING SET
Base unit
SET
MRP type
Non Stock
Criticality
A (3 of 3 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.8 SET/year: 0.1 unplanned (installed-base failure prior (no history)) + 0.7 from the maintenance plan.
  • 3.Lead time ~88 days; expected demand during lead time 0.7 (incl. 0.7 planned).
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 5.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 6.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Proposed purchase requisition
4 SET
Rp 15.4M · order by 01 Oct 2026
Expected arrival ≈ 88 days
Safety-critical (SCE)Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
100.0%
stockout risk now 100%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 12% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 1 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 51.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 3 functional locations

3 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-723
C3 RECYCLE FLOW CONTROL
A120.54
PX_PCV-1887C
BY PASS DUCT
A120.94
PX_SDV-245
ON-OFF VALVE
A110.06

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_SDV-245Final Element Overhaul; ONOFFV0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
07 Sept 2026LowPX_FCV-723[MSI-B-26-SFU-129/M] Replace line
25 Jun 2026MediumPX_PCV-1887CInstall cover plate for MCP cracking
16 Jul 2025MediumPX_PCV-1887CPCV-1887C stuck
30 May 2025LowPX_FCV-723Overhaul FCV-723
22 May 2025MediumPX_SDV-245PSM25/Check SDV-245.ok

Recent goods issues

Never issued in the 17-month history.