PACKING SET,VALVE,TYPE EE99,SS316

Material 4100045989 · PACKING SET · Plant 1000

ASafety-criticalLong-leadMonitorSlow-moving
Material
4100045989
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
A (2 of 5 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
80 d · P80 100 d
Unit price
Rp 3.0M

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 1.1 SET/year: 0.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
  • 3.Lead time ~80 days; expected demand during lead time 0.8 (incl. 0.7 planned).
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 5.Long lead time: 80% of deliveries took up to 100 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
  • 7.ML early warning: 37% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningSingle sourcePlanned demand in lead time
On hand / on order
5 / 0
no open PO
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 3.0M
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 493 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 343.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.

Installed on 5 functional locations

2 with criticality A/B · 11 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-816
BY PASS LINE
A130.54
PX_SDV-245
ON-OFF VALVE
A110.06
PX_PCV-1976B
BY PASS DUCT
C400.08
PX_FCV-1905D
HE-163D OUTLET FLOW
S100.11
PX_SDV-749
VD-756B SHUTDOWN VALVE
S400.06

Lead time and procurement

Lead time 80 ± 54 days (PO history, 3 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
13 May 2026PR03
Regular replenishment
2Rp 2.9M25 Jun 202643 d
22 Nov 2025PR03
Regular replenishment
1Rp 3.1M09 Apr 2026138 d
28 Jul 2025PR06
Regular replenishment
1Rp 3.0M01 Sept 202535 d

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Nov 2026PX_SDV-245Final Element Overhaul; ONOFFV0.72

Recent notifications on its equipment

DatePriorityFuncLocDescription
13 Dec 2025EmergencyPX_FCV-816[MSI-B-25-GPJ-391/M] Replace line
30 Sept 2025MediumPX_FCV-816Install scaffolding at FCV-816
22 May 2025MediumPX_SDV-245PSM25/Check SDV-245.ok
19 May 2025LowPX_FCV-816Leak from packing

Recent goods issues

Posting dateQtyOrderOrder type
26 May 20251201000004495Corrective
18 May 20251206000011347Other maintenance