PACKING SET,VALVE,TYPE EE99,SS316
Material 4100045989 · PACKING SET · Plant 1000
ASafety-criticalLong-leadMonitorSlow-moving
- Material
- 4100045989
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B, 2 safety/shutdown valve)
- Supplier
- KARYA ENERGI SENTOSA PT
- Lead time
- 80 d · P80 100 d
- Unit price
- Rp 3.0M
Recommendation
- 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 1.1 SET/year: 0.4 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 3.Lead time ~80 days; expected demand during lead time 0.8 (incl. 0.7 planned).
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 5.Long lead time: 80% of deliveries took up to 100 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
- 7.ML early warning: 37% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningSingle sourcePlanned demand in lead time
On hand / on order
5 / 0
no open PO
Today Min / Max
2 / 5
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
100.0%
stockout risk now 0%
Unit price
Rp 3.0M
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 493 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 343.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 5 functional locations
2 with criticality A/B · 11 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-816 BY PASS LINE | A | 1 | 3 | 0.54 |
| PX_SDV-245 ON-OFF VALVE | A | 1 | 1 | 0.06 |
| PX_PCV-1976B BY PASS DUCT | C | 4 | 0 | 0.08 |
| PX_FCV-1905D HE-163D OUTLET FLOW | S | 1 | 0 | 0.11 |
| PX_SDV-749 VD-756B SHUTDOWN VALVE | S | 4 | 0 | 0.06 |
Lead time and procurement
Lead time 80 ± 54 days (PO history, 3 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 May 2026 | PR03 Regular replenishment | 2 | Rp 2.9M | 25 Jun 2026 | 43 d |
| 22 Nov 2025 | PR03 Regular replenishment | 1 | Rp 3.1M | 09 Apr 2026 | 138 d |
| 28 Jul 2025 | PR06 Regular replenishment | 1 | Rp 3.0M | 01 Sept 2025 | 35 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_SDV-245 | Final Element Overhaul; ONOFFV | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 13 Dec 2025 | Emergency | PX_FCV-816 | [MSI-B-25-GPJ-391/M] Replace line |
| 30 Sept 2025 | Medium | PX_FCV-816 | Install scaffolding at FCV-816 |
| 22 May 2025 | Medium | PX_SDV-245 | PSM25/Check SDV-245.ok |
| 19 May 2025 | Low | PX_FCV-816 | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 May 2025 | 1 | 201000004495 | Corrective |
| 18 May 2025 | 1 | 206000011347 | Other maintenance |