PACKING SET,VALVE,MODEL GZ87,A105

Material 4100046172 · PACKING SET · Plant 1000

BReduceSlow-moving
Material
4100046172
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
B (2 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
88 d · P80 145 d
Unit price
Rp 3.8M (est.)

Recommendation

  • 1.Forecast 1.4 SET/year: 1.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~88 days; expected demand during lead time 0.3.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.Stock 7 exceeds the level to keep (6) by 1.
  • 5.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
7 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 3.8M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 245 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 148.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~38 days.

Installed on 3 functional locations

2 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-763
BY PASS DUCT
B120.51
PX_MOV-1377A
MOTOR OPERATED GATE VALVE
B110.06
PY_FCV-458
PP-448 OUTLET FLOW
C300.11

Lead time and procurement

Lead time 88 ± 50 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
01 Oct 2025LowPX_PCV-763[MSI-B-25-ZKV-115] Permanent repair
15 May 2025MediumPX_PCV-763PCV-763 stuck
05 May 2025HighPX_MOV-1377AReplace lamp as per PM finding

Recent goods issues

Posting dateQtyOrderOrder type
29 Jan 20263201000038591Corrective
09 Dec 20251201000013200Corrective