PACKING SET,VALVE,TYPE JY575,VITON

Material 4100046333 · PACKING SET · Plant 1000

CReorderHighStockout
Material
4100046333
Category
PACKING SET
Base unit
SET
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
LANGIT TEKNOLOGI PERSADA PT
Lead time
102 d · P80 145 d
Unit price
Rp 9.6M

Recommendation

  • 1.Forecast 1.8 SET/year: 1.8 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~102 days; expected demand during lead time 0.5.
  • 3.A 94.4% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
Proposed purchase requisition
4 SET
Rp 38.4M · order by 01 Oct 2026
Expected arrival ≈ 102 days
Single source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
94.4%
stockout risk now 32%
Unit price
Rp 9.6M
PO history
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 172 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 22.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~38 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-750B
HE-1481 OUTLET FLOW
C100.11
PY_FCV-680
HE-1822A OUTLET FLOW
C100.11

Lead time and procurement

Lead time 102 ± 50 days (PO history + category, 2 PO lines) · on-time 33%

PR dateTypeQtyUnit priceDeliveryLead time
08 Dec 2025PR03
Regular replenishment
1Rp 9.7M19 Feb 202673 d
20 Jul 2025PR03
Regular replenishment
1Rp 9.5M08 Jan 2026172 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
12 Apr 20262201000037398Corrective
22 Mar 20261201000024135Corrective
08 Jan 20261204000026906Preventive