PACKING SET,VALVE,SIZE KV351,PTFE
Material 4100046634 · PACKING SET · Plant 1000
ASafety-criticalLong-leadMaintainHealthy
- Material
- 4100046634
- Category
- PACKING SET
- Base unit
- SET
- MRP type
- Stock Item
- Criticality
- A (4 of 6 FuncLocs A/B, 1 safety/shutdown valve)
- Supplier
- RAJAWALI SEJAHTERA ABADI PT
- Lead time
- 96 d · P80 145 d
- Unit price
- Rp 1.4M
Recommendation
- 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 0.5 SET/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~96 days; expected demand during lead time 0.1.
- 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 5.Long lead time: 80% of deliveries took up to 145 days and the fastest seen in its category 38 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 6 FuncLoc(s), 4 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
1 / 2
next delivery 07 Dec 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 1.4M
PO history
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 152 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 386.3M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~38 days.
Installed on 6 functional locations
4 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1322 PP-743D TEMP CONTROL | A | 2 | 1 | 0.12 |
| PX_FCV-184B CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_SDV-626B VD-534A SHUTDOWN VALVE | A | 3 | 0 | 0.06 |
| PX_PCV-1940 VD-928B PRESSURE CONTROL | B | 1 | 0 | 0.08 |
| PX_TCV-1047 TEMPERATURE CONTROL VALVE | C | 1 | 0 | 0.12 |
| PX_FCV-832 CONTROL VALVE | S | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 96 ± 50 days (PO history + category, 1 PO lines) · on-time 36%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Aug 2026 | PR03 Regular replenishment | 2 | Rp 1.4M | 07 Dec 2026 open | 120 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 10 May 2025 | Medium | PX_TCV-1322 | Overhaul TCV-1322 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 May 2026 | 1 | 201000025318 | Corrective |