DIAPHRAGM,ACTUATOR,MODEL ZF286,MONEL
Material 4100046802 · DIAPHRAGM · Plant 1000
ALong-leadReduceExcess
- Material
- 4100046802
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (66 of 120 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 180 d · P80 237 d
- Unit price
- Rp 3.9M
Recommendation
- 1.Forecast 30 EA/year: 25 unplanned (recency-weighted compound poisson (own history)) + 5.0 from the maintenance plan.
- 2.Lead time ~180 days; expected demand during lead time 16 (incl. 3.6 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 37, order up to 48.
- 4.Stock 99 exceeds the level to keep (48) by 51.
- 5.Long lead time: 80% of deliveries took up to 237 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 120 FuncLoc(s), 66 of them criticality A/B.
- 7.ML early warning: 100% probability of demand in the next 90 days.
Long-leadML early warningLast turnaround used 13Single sourceOpen POPlanned demand in lead time
On hand / on order
99 / 102
next delivery 02 Oct 2026
Today Min / Max
67 / 108
static parameters in BoM
Rec. Min (reorder point)
37
safety stock 22
Rec. Max
48
order qty 11
Service level
99.9%
stockout risk now 0%
Unit price
Rp 3.9M
PO history
ML early warning: 100% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 5 issue days in the last 180 days, last issue 5 days ago, 9 failure notifications on its equipment in 90 days, 3 planned jobs in 90 days, 7 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (13 units) excluded from the baseline.
Demand pattern Erratic · 29 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 16.9B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 120 functional locations
66 with criticality A/B · 162 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-1444A BY PASS LINE | A | 1 | 5 | 2.25 |
| PX_PCV-1960 PRESSURE CONTROL VALVE | A | 1 | 4 | 0.94 |
| PX_FCV-235B VD-719 OUTLET FLOW | A | 1 | 3 | 0.96 |
| PX_FCV-1033A PP-1597B OUTLET FLOW | A | 4 | 2 | 0.54 |
| PX_FCV-1644 VD-981A OUTLET FLOW | A | 1 | 2 | 0.11 |
| PX_TCV-1826B PP-1139 TEMP CONTROL | A | 3 | 2 | 0.55 |
| PX_TCV-413C TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.12 |
| PX_TCV-868 TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.55 |
| PX_LCV-1581 LEVEL CONTROL VALVE | A | 1 | 1 | 0.12 |
| PX_PCV-143A HE-1596B PRESSURE CONTROL | A | 1 | 1 | 0.08 |
| PX_PCV-655B BY PASS DUCT | A | 1 | 1 | 0.08 |
| PX_TCV-1203B TEMPERATURE CONTROL VALVE | A | 1 | 1 | 0.55 |
Lead time and procurement
Lead time 180 ± 70 days (PO history, 15 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Aug 2026 | PR03 Regular replenishment | 13 | Rp 3.8M | 04 Jan 2027 open | 143 d |
| 14 Jul 2026 | PR06 Regular replenishment | 11 | Rp 4.0M | 02 Oct 2026 open | 80 d |
| 18 Jun 2026 | PR03 Regular replenishment | 8 | Rp 3.8M | 30 Oct 2026 open | 134 d |
| 14 Jun 2026 | PR06 Regular replenishment | 9 | Rp 3.8M | 05 Nov 2026 open | 144 d |
| 22 May 2026 | PR03 Regular replenishment | 20 | Rp 3.9M | 27 Oct 2026 open | 158 d |
| 14 May 2026 | PR03 Regular replenishment | 26 | Rp 3.9M | 23 Oct 2026 open | 162 d |
| 07 Apr 2026 | PR03 Regular replenishment | 8 | Rp 3.9M | 23 Oct 2026 open | 199 d |
| 26 Jan 2026 | PR03 Regular replenishment | 16 | Rp 3.9M | 28 Aug 2026 | 214 d |
| 22 Jan 2026 | PR05 Project / turnaround | 12 | Rp 3.8M | 16 Sept 2026 | 237 d |
| 12 Dec 2025 | PR06 Regular replenishment | 7 | Rp 3.8M | 06 Dec 2026 open | 359 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 24 Oct 2026 | PX_LCV-1730C | Final Element Overhaul; Control Valve | 0.72 |
| 01 Dec 2026 | PX_PCV-645 | Final Element Overhaul; Control Valve | 0.72 |
| 01 Dec 2026 | PX_LCV-825 | Final Element Overhaul; CV | 1.43 |
| 19 Feb 2027 | PX_PCV-1400B | Final Element Overhaul; Control Valve | 0.72 |
| 12 Aug 2027 | PY_LCV-375 | Final Element Overhaul; CV | 0.72 |
| 01 Sept 2027 | PX_LCV-775 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Sept 2026 | Medium | PX_FCV-763A | FCV-763A; valve hunting |
| 17 Sept 2026 | Low | PX_FCV-651 | Overhaul FCV-651 |
| 13 Sept 2026 | High | PX_LCV-1691A | [MSI-B-26-KJJ-391/M] Replace line |
| 11 Sept 2026 | Low | PY_TCV-441A | Replace lamp as per PM finding |
| 20 Aug 2026 | Medium | PX_FCV-651 | [MSI-B-26-RWX-113/M] Replace line |
| 19 Aug 2026 | Medium | PX_FCV-235B | FCV-235B; valve hunting |
| 18 Aug 2026 | High | PX_TCV-413C | Install scaffolding at TCV-413C |
| 17 Aug 2026 | Medium | PX_FCV-1644 | Install scaffolding at FCV-1644 |
| 22 Jul 2026 | Medium | PX_LCV-1691A | LCV-1691A; small leak at packing |
| 15 Jul 2026 | High | PX_LCV-1986 | Repair insulation LCV-1986 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 26 Sept 2026 | 1 | 201000028026 | Corrective |
| 02 Sept 2026 | 1 | 201000023287 | Corrective |
| 07 Jun 2026 | 1 | 201000009658 | Corrective |
| 01 May 2026 | 1 | 201000004547 | Corrective |
| 11 Apr 2026 | 1 | 201000037398 | Corrective |
| 31 Mar 2026 | 3 | 201000027435 | Corrective |
| 24 Feb 2026 | 2 | 201000001108 | Corrective |
| 26 Jan 2026 | 1 | 201000028573 | Corrective |
| 23 Jan 2026 | 1 | 201000022788 | Corrective |
| 22 Jan 2026 | 1 | 201000035525 | Corrective |
| 19 Jan 2026 | 2 | 201000006546 | Corrective |
| 12 Jan 2026 | 2 | 201000008132 | Corrective |
| 27 Dec 2025 | 2 | 203000001878 | Turnaround |
| 26 Dec 2025 | 1 | 203000001878 | Turnaround |
| 26 Dec 2025 | 2 | 203000001878 | Turnaround |