DIAPHRAGM,ACTUATOR,MODEL VI156,A182F11
Material 4100046824 · DIAPHRAGM · Plant 1000
ALong-leadReduceExcess
- Material
- 4100046824
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (20 of 46 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 104 d · P80 141 d
- Unit price
- Rp 2.9M
Recommendation
- 1.Forecast 11 EA/year: 11 unplanned (recency-weighted compound poisson (own history)) + 0.7 from the maintenance plan.
- 2.Lead time ~104 days; expected demand during lead time 3.8 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 12, order up to 20.
- 4.Stock 85 exceeds the level to keep (20) by 65.
- 5.Long lead time: 80% of deliveries took up to 141 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 46 FuncLoc(s), 20 of them criticality A/B.
- 7.ML early warning: 89% probability of demand in the next 90 days.
Long-leadML early warningSingle sourceOpen POPlanned demand in lead time
On hand / on order
85 / 8
next delivery 28 Jan 2027
Today Min / Max
18 / 46
static parameters in BoM
Rec. Min (reorder point)
12
safety stock 9
Rec. Max
20
order qty 8
Service level
99.9%
stockout risk now 0%
Unit price
Rp 2.9M
PO history
ML early warning: 89% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 3 issue days in the last 180 days, last issue 88 days ago, 2 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 2 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 13 issue days · method: Recency-weighted compound Poisson (own history).
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 8.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 46 functional locations
20 with criticality A/B · 48 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-529A RICH AMINE FLOW CONTROL | A | 1 | 7 | 2.25 |
| PY_LCV-744 VD-1378 LEVEL CONTROL | A | 1 | 3 | 0.55 |
| PX_TCV-816 HE-234C TEMP CONTROL | A | 1 | 2 | 0.55 |
| PX_LCV-1581 LEVEL CONTROL VALVE | A | 2 | 1 | 0.12 |
| PX_FCV-1152 RECYCLE ETHANE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_FCV-1264A CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-1514A RECYCLE ETHANE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_PCV-392A BY PASS DUCT | A | 1 | 0 | 0.08 |
| PX_TCV-946 TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_LCV-589B PP-389 LEVEL CONTROL | B | 1 | 2 | 0.55 |
| PX_FCV-408 QUENCH OIL FLOW CONTROL | B | 1 | 1 | 0.54 |
| PX_FCV-1638B PP-135A OUTLET FLOW | B | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 104 ± 59 days (PO history, 8 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 14 Aug 2026 | PR03 Regular replenishment | 8 | Rp 2.9M | 28 Jan 2027 open | 167 d |
| 12 May 2026 | PR03 Regular replenishment | 8 | Rp 2.8M | 08 Sept 2026 | 119 d |
| 21 Jan 2026 | PR03 Regular replenishment | 7 | Rp 2.8M | 29 Mar 2026 | 67 d |
| 09 Jan 2026 | PR03 Regular replenishment | 10 | Rp 2.8M | 06 Mar 2026 | 56 d |
| 01 Jan 2026 | PR03 Regular replenishment | 9 | Rp 3.0M | 09 Apr 2026 | 98 d |
| 18 Dec 2025 | PR06 Regular replenishment | 5 | Rp 2.9M | 02 Feb 2026 | 46 d |
| 04 Aug 2025 | PR06 Regular replenishment | 4 | Rp 3.0M | 06 Jan 2026 | 155 d |
| 24 Jul 2025 | PR03 Regular replenishment | 9 | Rp 2.8M | 30 Aug 2025 | 37 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Nov 2026 | PX_TCV-816 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Sept 2026 | Medium | PX_PCV-165C | [MSI-B-26-AJT-261] Permanent repair |
| 02 Sept 2026 | Medium | PX_FCV-529A | Install scaffolding at FCV-529A |
| 22 Aug 2026 | Medium | PX_PCV-1130A | PCV-1130A; small leak at packing |
| 06 Jun 2026 | Low | PX_PCV-1130A | Replace lamp as per PM finding |
| 30 May 2026 | Low | PX_LCV-589B | LCV-589B stuck |
| 17 May 2026 | Medium | PX_FCV-529A | FCV-529A; IA leak from regulator |
| 15 May 2026 | Medium | PY_LCV-744 | LCV-744; small leak at packing |
| 12 May 2026 | Medium | PX_PCV-165C | Install scaffolding at PCV-165C |
| 10 May 2026 | Medium | PX_TCV-816 | TCV-816; valve hunting |
| 07 May 2026 | Medium | PY_LCV-744 | Painting LCV-744 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Jul 2026 | 1 | 201000035938 | Corrective |
| 22 Apr 2026 | 2 | 201000039422 | Corrective |
| 22 Apr 2026 | 1 | 201000039422 | Corrective |
| 12 Apr 2026 | 1 | 201000037398 | Corrective |
| 23 Mar 2026 | 1 | 201000019498 | Corrective |
| 22 Mar 2026 | 1 | 201000024135 | Corrective |
| 18 Feb 2026 | 1 | 201000003328 | Corrective |
| 19 Jan 2026 | 1 | 201000000305 | Corrective |
| 09 Jan 2026 | 1 | 201000039073 | Corrective |
| 15 Dec 2025 | 2 | 201000009664 | Corrective |
| 01 Dec 2025 | 1 | 201000002672 | Corrective |
| 20 Nov 2025 | 2 | 201000018732 | Corrective |
| 05 Oct 2025 | 1 | 201000008983 | Corrective |
| 21 Aug 2025 | 1 | 201000031456 | Corrective |