DIAPHRAGM,ACTUATOR,TYPE VB425,SS316
Material 4100046847 · DIAPHRAGM · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100046847
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (10 of 19 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 117 d · P80 132 d
- Unit price
- Rp 8.7M
Recommendation
- 1.Forecast 2.3 EA/year: 1.6 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~117 days; expected demand during lead time 0.5.
- 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Long lead time: 80% of deliveries took up to 132 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 19 FuncLoc(s), 10 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 52.3M · order by 01 Oct 2026
Expected arrival ≈ 117 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
100.0%
stockout risk now 40%
Unit price
Rp 8.7M
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 332 days ago, 3 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.6B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 19 functional locations
10 with criticality A/B · 21 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1256 PP-1570A TEMP CONTROL | A | 1 | 4 | 1.40 |
| PX_PCV-527B PRESSURE CONTROL VALVE | A | 1 | 1 | 0.08 |
| PY_LCV-1700 VD-1637 LEVEL CONTROL | A | 1 | 1 | 0.12 |
| PX_FCV-1081A CONTROL VALVE | A | 1 | 0 | 0.11 |
| PX_FCV-665 VD-339 OUTLET FLOW | B | 1 | 2 | 0.54 |
| PX_FCV-1021 DEMIN WATER FLOW CONTROL | B | 1 | 0 | 0.11 |
| PX_FCV-1753 BY PASS LINE | B | 1 | 0 | 0.11 |
| PX_TCV-1095 HE-882D TEMP CONTROL | B | 1 | 0 | 0.12 |
| PX_TCV-776 TEMPERATURE CONTROL VALVE | B | 1 | 0 | 0.12 |
| PY_LCV-1056 LEVEL CONTROL VALVE | B | 1 | 0 | 0.12 |
| PX_FCV-919A DEMIN WATER FLOW CONTROL | C | 1 | 2 | 0.54 |
| PX_LCV-1043 KC-279C LEVEL CONTROL | C | 3 | 0 | 0.12 |
Lead time and procurement
Lead time 117 ± 69 days (PO history, 3 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 17 Feb 2026 | PR06 Regular replenishment | 2 | Rp 8.7M | 29 Jul 2026 | 162 d |
| 28 Jul 2025 | PR06 Regular replenishment | 2 | Rp 8.7M | 19 Sept 2025 | 53 d |
| 26 May 2025 | PR03 Regular replenishment | 1 | Rp 9.3M | 21 Aug 2025 | 87 d |
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Sept 2027 | PX_LCV-775 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 Sept 2026 | Medium | PX_TCV-1934 | TCV-1934; IA leak from regulator |
| 30 Jul 2026 | Low | PX_TCV-1256 | TCV-1256; IA leak from regulator |
| 29 Jul 2026 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
| 30 Jun 2026 | Medium | PX_FCV-919A | FCV-919A; IA leak from regulator |
| 01 May 2026 | Low | PX_FCV-665 | FCV-665; valve hunting |
| 16 Apr 2026 | Medium | PX_TCV-1256 | Replace lamp as per PM finding |
| 18 Jun 2025 | Low | PX_TCV-1934 | TCV-1934 passing |
| 25 May 2025 | Low | PX_FCV-665 | Repair insulation FCV-665 |
| 19 May 2025 | Medium | PY_LCV-1700 | LCV-1700; small leak at packing |
| 17 May 2025 | Low | PX_FCV-919A | PSM25/FCV-919A; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Nov 2025 | 1 | 201000038265 | Corrective |