DIAPHRAGM,ACTUATOR,MODEL CD343,A105
Material 4100046969 · DIAPHRAGM · Plant 1000
AReduceSlow-moving
- Material
- 4100046969
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (8 of 11 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 134 d · P80 191 d
- Unit price
- Rp 4.4M (est.)
Recommendation
- 1.Forecast 2.7 EA/year: 2.0 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~134 days; expected demand during lead time 1.4 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
- 4.Stock 50 exceeds the level to keep (9) by 41.
- 5.Installed on 11 FuncLoc(s), 8 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
50 / 0
no open PO
Today Min / Max
2 / 3
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
9
order qty 3
Service level
99.9%
stockout risk now 0%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 28% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 275 days ago, 0 failure notifications on its equipment in 90 days, 1 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.2B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 11 functional locations
8 with criticality A/B · 14 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-413C TEMPERATURE CONTROL VALVE | A | 1 | 2 | 0.12 |
| PX_PCV-1307B PRESSURE CONTROL VALVE | A | 2 | 1 | 0.08 |
| PX_FCV-1088 BY PASS LINE | A | 1 | 0 | 0.11 |
| PX_FCV-823 C4 PRODUCT FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_TCV-1552B TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_TCV-1965A PP-915A TEMP CONTROL | A | 1 | 0 | 0.12 |
| PX_PCV-1103 PRESSURE CONTROL VALVE | B | 3 | 3 | 0.51 |
| PX_FCV-1990A SEAL OIL FLOW CONTROL | B | 1 | 0 | 0.11 |
| PX_FCV-1562 CAUSTIC FLOW CONTROL | C | 1 | 1 | 0.11 |
| PX_LCV-1273 PP-200D LEVEL CONTROL | C | 1 | 0 | 0.12 |
| PX_TCV-1082A HE-171A TEMP CONTROL | S | 1 | 1 | 0.55 |
Lead time and procurement
Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Dec 2026 | PX_TCV-1082A | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 18 Aug 2026 | High | PX_TCV-413C | Install scaffolding at TCV-413C |
| 26 Jun 2026 | Medium | PX_PCV-1103 | PCV-1103; IA leak from regulator |
| 29 Sept 2025 | Medium | PX_PCV-1103 | Install scaffolding at PCV-1103 |
| 01 Jul 2025 | Medium | PX_TCV-1082A | Leak from packing |
| 28 May 2025 | Low | PX_FCV-1562 | Overhaul FCV-1562 |
| 28 May 2025 | Low | PX_TCV-413C | TCV-413C stuck |
| 09 May 2025 | Medium | PX_PCV-1103 | [MSI-B-25-XXZ-362/M] Replace line |
| 05 May 2025 | Low | PX_PCV-1307B | PCV-1307B; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 30 Dec 2025 | 1 | 201000025312 | Corrective |
| 19 Nov 2025 | 1 | 201000016105 | Corrective |
| 07 Sept 2025 | 3 | 201000005017 | Corrective |