DIAPHRAGM,ACTUATOR,SIZE MM165,SS304
Material 4100047077 · DIAPHRAGM · Plant 1000
AReorderNormalSlow-moving
- Material
- 4100047077
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (2 of 5 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 134 d · P80 191 d
- Unit price
- Rp 4.4M (est.)
Recommendation
- 1.Forecast 2.7 EA/year: 2.7 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~134 days; expected demand during lead time 1.0.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 6, order up to 9.
- 4.On hand 4 + on order 0 is at or below the reorder point: order 5 now.
- 5.Installed on 5 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 21.9M · order by 01 Oct 2026
Expected arrival ≈ 134 days
Price estimatedLead time estimated
On hand / on order
4 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
6
safety stock 5
Rec. Max
9
order qty 3
Service level
99.8%
stockout risk now 1%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 212 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 3 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.3B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 5 functional locations
2 with criticality A/B · 6 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1300B BY PASS DUCT | A | 1 | 4 | 0.94 |
| PX_PCV-318 PRESSURE CONTROL VALVE | B | 1 | 0 | 0.08 |
| PX_TCV-745 PP-1161 TEMP CONTROL | C | 2 | 3 | 0.98 |
| PY_FCV-458 PP-448 OUTLET FLOW | C | 1 | 0 | 0.11 |
| PX_PCV-1276 PP-1899 PRESSURE CONTROL | S | 1 | 0 | 0.08 |
Lead time and procurement
Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Sept 2026 | Low | PX_TCV-745 | TCV-745; IA leak from regulator |
| 27 Jul 2026 | Medium | PX_TCV-745 | Install cover plate for MCP cracking |
| 29 May 2026 | Medium | PX_PCV-1300B | PCV-1300B; small leak at packing |
| 24 Mar 2026 | High | PX_PCV-1300B | Painting PCV-1300B |
| 20 Aug 2025 | Medium | PX_PCV-1300B | Leak from packing |
| 22 Jul 2025 | Low | PX_TCV-745 | Install scaffolding at TCV-745 |
| 28 May 2025 | Medium | PX_PCV-1300B | Leak from packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 03 Mar 2026 | 1 | 201000006597 | Corrective |
| 03 Mar 2026 | 2 | 201000006597 | Corrective |
| 12 Dec 2025 | 1 | 201000008455 | Corrective |
| 09 Oct 2025 | 2 | 204000002500 | Preventive |