DIAPHRAGM,ACTUATOR,SIZE BN577,NBR
Material 4100047204 · DIAPHRAGM · Plant 1000
AReduceSlow-moving
- Material
- 4100047204
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (6 of 10 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 134 d · P80 191 d
- Unit price
- Rp 4.4M (est.)
Recommendation
- 1.Forecast 1.2 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior) + 0.7 from the maintenance plan.
- 2.Lead time ~134 days; expected demand during lead time 0.9 (incl. 0.7 planned).
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
- 4.Stock 122 exceeds the level to keep (5) by 117.
- 5.Installed on 10 FuncLoc(s), 6 of them criticality A/B.
Planned demand in lead timePrice estimatedLead time estimated
On hand / on order
122 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 17% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 318 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 469.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.
Installed on 10 functional locations
6 with criticality A/B · 13 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1344 TEMPERATURE CONTROL VALVE | A | 1 | 1 | 0.12 |
| PX_FCV-763 BY PASS LINE | A | 4 | 0 | 0.11 |
| PX_FCV-933A RECYCLE ETHANE FLOW CONTROL | A | 1 | 0 | 0.11 |
| PX_LCV-1062A LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_LCV-1722A PP-1760A LEVEL CONTROL | A | 1 | 0 | 0.12 |
| PX_FCV-938C BY PASS LINE | B | 1 | 0 | 0.11 |
| PX_FCV-1206B BOTTOM FLOW CONTROL | C | 1 | 0 | 0.11 |
| PX_FCV-1884 BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_FCV-1932 BY PASS LINE | C | 1 | 0 | 0.11 |
| PX_LCV-622 LEVEL CONTROL VALVE | C | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
| Due | FuncLoc | Job | Qty |
|---|---|---|---|
| 01 Feb 2027 | PX_FCV-1932 | Final Element Overhaul; Control Valve | 0.72 |
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 27 May 2025 | High | PX_TCV-1344 | TCV-1344; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 17 Nov 2025 | 1 | 201000004355 | Corrective |