DIAPHRAGM,ACTUATOR,SIZE VP853,VITON

Material 4100047259 · DIAPHRAGM · Plant 1000

AReorderCriticalSlow-moving
Material
4100047259
Category
DIAPHRAGM
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 6 FuncLocs A/B)
Supplier
No PO history
Lead time
134 d · P80 191 d
Unit price
Rp 4.4M (est.)

Recommendation

  • 1.Forecast 2.9 EA/year: 0.1 unplanned (installed-base failure prior (no history)) + 2.9 from the maintenance plan.
  • 2.Lead time ~134 days; expected demand during lead time 2.9 (incl. 2.9 planned).
  • 3.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 7.
  • 4.On hand 2 + on order 0 is at or below the reorder point: order 5 now.
  • 5.Installed on 6 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 21.9M · order by 01 Oct 2026
Expected arrival ≈ 134 days
Convert to Stock ItemPlanned demand in lead timePrice estimatedLead time estimated
On hand / on order
2 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 2
Rec. Max
7
order qty 3
Service level
100.0%
stockout risk now 100%
Unit price
Rp 4.4M
Category + unit estimate
ML early warning: 10% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 463 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 57.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~46 days.

Installed on 6 functional locations

1 with criticality A/B · 12 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1732
BFW FLOW CONTROL
A410.11
PX_PCV-258
HE-1843C PRESSURE CONTROL
C130.94
PX_LCV-993C
HE-1251C LEVEL CONTROL
C100.12
PX_PCV-540A
PRESSURE CONTROL VALVE
C100.08
PX_TCV-1394B
PP-118B TEMP CONTROL
C100.12
PY_PCV-922B
BY PASS DUCT
C400.08

Lead time and procurement

Lead time 134 ± 82 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

DueFuncLocJobQty
01 Feb 2027PX_FCV-1732Final Element Overhaul; Control Valve2.86

Recent notifications on its equipment

DatePriorityFuncLocDescription
05 Mar 2026LowPX_PCV-258PCV-258; valve hunting
10 Sept 2025MediumPX_PCV-258Replace lamp as per PM finding
25 May 2025MediumPX_FCV-1732PSM25/FCV-1732 passing
24 May 2025LowPX_PCV-258PCV-258; valve hunting

Recent goods issues

Posting dateQtyOrderOrder type
25 Jun 20252204000014982Preventive