DIAPHRAGM,ACTUATOR,MODEL XO536,PTFE
Material 4100047323 · DIAPHRAGM · Plant 1000
BLong-leadReorderCriticalStockout
- Material
- 4100047323
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 3 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 122 d · P80 171 d
- Unit price
- Rp 4.3M
Recommendation
- 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~122 days; expected demand during lead time 0.4.
- 3.A 98.6% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
- 5.Long lead time: 80% of deliveries took up to 171 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 17.2M · order by 01 Oct 2026
Expected arrival ≈ 122 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
98.6%
stockout risk now 16%
Unit price
Rp 4.3M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 272 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 130.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~46 days.
Installed on 3 functional locations
1 with criticality A/B · 4 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1010D PRESSURE CONTROL VALVE | B | 2 | 0 | 0.08 |
| PX_LCV-1273 PP-200D LEVEL CONTROL | C | 1 | 0 | 0.12 |
| PX_PCV-1757B PRESSURE CONTROL VALVE | S | 1 | 0 | 0.08 |
Lead time and procurement
Lead time 122 ± 76 days (PO history, 4 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 12 Nov 2025 | PR03 Regular replenishment | 2 | Rp 4.3M | 02 Jan 2026 | 51 d |
| 13 Oct 2025 | PR01 Import / long-lead | 2 | Rp 4.3M | 21 Mar 2026 | 159 d |
| 18 Sept 2025 | PR03 Regular replenishment | 1 | Rp 4.1M | 08 Nov 2025 | 51 d |
| 31 Jul 2025 | PR03 Regular replenishment | 1 | Rp 4.4M | 06 Feb 2026 | 190 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 02 Jan 2026 | 2 | 201000026775 | Corrective |
| 02 Jan 2026 | 1 | 201000026775 | Corrective |
| 12 Sept 2025 | 1 | 201000001258 | Corrective |