Sparely
DU

DIAPHRAGM,ACTUATOR,MODEL XO536,PTFE

Material 4100047323 · DIAPHRAGM · Plant 1000

BLong-leadReorderCriticalStockout
Material
4100047323
Category
DIAPHRAGM
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 3 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
122 d · P80 171 d
Unit price
Rp 4.3M

Recommendation

  • 1.Forecast 1.1 EA/year: 1.1 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~122 days; expected demand during lead time 0.4.
  • 3.A 98.6% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 4 now.
  • 5.Long lead time: 80% of deliveries took up to 171 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Proposed purchase requisition
4 EA
Rp 17.2M · order by 01 Oct 2026
Expected arrival ≈ 122 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
98.6%
stockout risk now 16%
Unit price
Rp 4.3M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 272 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 130.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~46 days.

Installed on 3 functional locations

1 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1010D
PRESSURE CONTROL VALVE
B200.08
PX_LCV-1273
PP-200D LEVEL CONTROL
C100.12
PX_PCV-1757B
PRESSURE CONTROL VALVE
S100.08

Lead time and procurement

Lead time 122 ± 76 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
12 Nov 2025PR03
Regular replenishment
2Rp 4.3M02 Jan 202651 d
13 Oct 2025PR01
Import / long-lead
2Rp 4.3M21 Mar 2026159 d
18 Sept 2025PR03
Regular replenishment
1Rp 4.1M08 Nov 202551 d
31 Jul 2025PR03
Regular replenishment
1Rp 4.4M06 Feb 2026190 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
02 Jan 20262201000026775Corrective
02 Jan 20261201000026775Corrective
12 Sept 20251201000001258Corrective