DIAPHRAGM,ACTUATOR,MODEL OB629,SS316
Material 4100048174 · DIAPHRAGM · Plant 1000
BLong-leadMonitorSlow-moving
- Material
- 4100048174
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 3 FuncLocs A/B)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 144 d · P80 191 d
- Unit price
- Rp 10.6M
Recommendation
- 1.Forecast 1.0 EA/year: 1.0 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~144 days; expected demand during lead time 0.4.
- 3.A 99.2% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 6.
- 4.Long lead time: 80% of deliveries took up to 191 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 3 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle source
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
6
order qty 3
Service level
99.2%
stockout risk now 1%
Unit price
Rp 10.6M
PO history
ML early warning: 14% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 210 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 81.1M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~46 days.
Installed on 3 functional locations
1 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_LCV-706 VD-694 LEVEL CONTROL | B | 1 | 0 | 0.12 |
| PX_PCV-1776A BY PASS DUCT | C | 1 | 0 | 0.08 |
| PX_FCV-1905D HE-163D OUTLET FLOW | S | 1 | 0 | 0.11 |
Lead time and procurement
Lead time 144 ± 82 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 13 Apr 2026 | PR03 Regular replenishment | 1 | Rp 10.5M | 09 Sept 2026 | 149 d |
| 10 Jul 2025 | PR06 Regular replenishment | 2 | Rp 10.6M | 28 Dec 2025 | 171 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 05 Mar 2026 | 3 | 201000004588 | Corrective |