Sparely
DU

DIAPHRAGM,ACTUATOR,MODEL WA139,CS

Material 4100048395 · DIAPHRAGM · Plant 1000

BLong-leadMaintainHealthy
Material
4100048395
Category
DIAPHRAGM
Base unit
EA
MRP type
Stock Item
Criticality
B (1 of 1 FuncLocs A/B)
Supplier
PRIMA SUPLINDO JAYA PT
Lead time
131 d · P80 172 d
Unit price
Rp 10.7M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~131 days; expected demand during lead time 0.2.
  • 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 4.Long lead time: 80% of deliveries took up to 172 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
2 / 4
next delivery 21 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.9%
stockout risk now 0%
Unit price
Rp 10.7M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 161 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 107.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~46 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_PCV-1103
PRESSURE CONTROL VALVE
B130.51

Lead time and procurement

Lead time 131 ± 73 days (PO history, 5 PO lines) · on-time 32%

PR dateTypeQtyUnit priceDeliveryLead time
15 Sept 2026PR06
Regular replenishment
1Rp 10.9M21 Oct 2026
open
36 d
28 Aug 2026PR03
Regular replenishment
2Rp 10.7M10 Dec 2026
open
104 d
20 Jun 2026PR06
Regular replenishment
1Rp 10.2M28 Nov 2026
open
161 d
22 Feb 2026PR03
Regular replenishment
1Rp 10.3M28 Sept 2026218 d
03 Sept 2025PR03
Regular replenishment
1Rp 10.8M07 Jan 2026126 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
26 Jun 2026MediumPX_PCV-1103PCV-1103; IA leak from regulator
29 Sept 2025MediumPX_PCV-1103Install scaffolding at PCV-1103
09 May 2025MediumPX_PCV-1103[MSI-B-25-XXZ-362/M] Replace line

Recent goods issues

Posting dateQtyOrderOrder type
23 Apr 20261204000001034Preventive