DIAPHRAGM,ACTUATOR,MODEL WA139,CS
Material 4100048395 · DIAPHRAGM · Plant 1000
BLong-leadMaintainHealthy
- Material
- 4100048395
- Category
- DIAPHRAGM
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- B (1 of 1 FuncLocs A/B)
- Supplier
- PRIMA SUPLINDO JAYA PT
- Lead time
- 131 d · P80 172 d
- Unit price
- Rp 10.7M
Recommendation
- 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~131 days; expected demand during lead time 0.2.
- 3.A 98.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Long lead time: 80% of deliveries took up to 172 days and the fastest seen in its category 46 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 5.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
2 / 4
next delivery 21 Oct 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.9%
stockout risk now 0%
Unit price
Rp 10.7M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 161 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 3 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 107.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~46 days.
Installed on 1 functional locations
1 with criticality A/B · 1 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1103 PRESSURE CONTROL VALVE | B | 1 | 3 | 0.51 |
Lead time and procurement
Lead time 131 ± 73 days (PO history, 5 PO lines) · on-time 32%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 15 Sept 2026 | PR06 Regular replenishment | 1 | Rp 10.9M | 21 Oct 2026 open | 36 d |
| 28 Aug 2026 | PR03 Regular replenishment | 2 | Rp 10.7M | 10 Dec 2026 open | 104 d |
| 20 Jun 2026 | PR06 Regular replenishment | 1 | Rp 10.2M | 28 Nov 2026 open | 161 d |
| 22 Feb 2026 | PR03 Regular replenishment | 1 | Rp 10.3M | 28 Sept 2026 | 218 d |
| 03 Sept 2025 | PR03 Regular replenishment | 1 | Rp 10.8M | 07 Jan 2026 | 126 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 26 Jun 2026 | Medium | PX_PCV-1103 | PCV-1103; IA leak from regulator |
| 29 Sept 2025 | Medium | PX_PCV-1103 | Install scaffolding at PCV-1103 |
| 09 May 2025 | Medium | PX_PCV-1103 | [MSI-B-25-XXZ-362/M] Replace line |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 23 Apr 2026 | 1 | 204000001034 | Preventive |