POSITIONER,VALVE,TYPE AF626,SS316
Material 4100048663 · POSITIONER · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100048663
- Category
- POSITIONER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (7 of 9 FuncLocs A/B)
- Supplier
- GUNUNG PERKASA NUSANTARA PT
- Lead time
- 152 d · P80 166 d
- Unit price
- Rp 24.3M
Recommendation
- 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~152 days; expected demand during lead time 0.6.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 5, order up to 8.
- 4.On hand 0 + on order 3 is at or below the reorder point: order 5 now.
- 5.Long lead time: 80% of deliveries took up to 166 days and the fastest seen in its category 40 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 9 FuncLoc(s), 7 of them criticality A/B.
Proposed purchase requisition
5 EA
Rp 121.6M · order by 01 Oct 2026
Expected arrival ≈ 152 days
Long-leadSingle sourceOpen PO
On hand / on order
0 / 3
next delivery 02 Jan 2027
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
5
safety stock 5
Rec. Max
8
order qty 3
Service level
99.8%
stockout risk now 3%
Unit price
Rp 24.3M
PO history
ML early warning: 29% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 313 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 521.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~40 days.
Installed on 9 functional locations
7 with criticality A/B · 12 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1709B BY PASS DUCT | A | 1 | 1 | 0.08 |
| PX_LCV-184 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_PCV-585A VD-1188A PRESSURE CONTROL | A | 1 | 0 | 0.08 |
| PX_PCV-655 PRESSURE CONTROL VALVE | B | 1 | 1 | 0.08 |
| PX_FCV-1525A CONTROL VALVE | B | 1 | 0 | 0.11 |
| PX_FCV-171A BY PASS LINE | B | 1 | 0 | 0.11 |
| PX_TCV-529 TEMPERATURE CONTROL VALVE | B | 1 | 0 | 0.12 |
| PX_TCV-252C PP-1139 TEMP CONTROL | S | 1 | 0 | 0.12 |
| PY_PCV-649 BY PASS DUCT | S | 4 | 0 | 0.08 |
Lead time and procurement
Lead time 152 ± 64 days (PO history + category, 2 PO lines) · on-time 35%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 10 Sept 2026 | PR03 Regular replenishment | 1 | Rp 24.9M | 14 Jan 2027 open | 126 d |
| 17 Jan 2026 | PR06 Regular replenishment | 2 | Rp 23.8M | 02 Jan 2027 open | 350 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 28 May 2025 | Medium | PX_PCV-1709B | PCV-1709B; small leak at packing |
| 19 May 2025 | Medium | PX_PCV-655 | PCV-655 stuck |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 22 Nov 2025 | 4 | 201000030518 | Corrective |
| 24 Aug 2025 | 1 | 201000006861 | Corrective |