POSITIONER,VALVE,TYPE OW115,CS

Material 4100048706 · POSITIONER · Plant 1000

ALong-leadReduceExcess
Material
4100048706
Category
POSITIONER
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 3 FuncLocs A/B)
Supplier
GUNUNG PERKASA NUSANTARA PT
Lead time
99 d · P80 166 d
Unit price
Rp 26.1M

Recommendation

  • 1.Forecast 1.3 EA/year: 1.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~99 days; expected demand during lead time 0.3.
  • 3.A 99.5% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 4.Stock 18 exceeds the level to keep (3) by 15.
  • 5.Long lead time: 80% of deliveries took up to 166 days and the fastest seen in its category 40 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Long-leadConvert to Stock ItemSingle source
On hand / on order
18 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.5%
stockout risk now 0%
Unit price
Rp 26.1M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 5 days ago, 1 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~40 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1156C
PP-1323A OUTLET FLOW
A100.11
PX_PCV-1453
PRESSURE CONTROL VALVE
A100.08
PX_FCV-274A
HE-1596B OUTLET FLOW
C130.96

Lead time and procurement

Lead time 99 ± 64 days (PO history + category, 1 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
27 May 2025PR06
Regular replenishment
1Rp 26.1M15 Sept 2025111 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
28 Aug 2026MediumPX_FCV-274AFCV-274A; IA leak from regulator
14 Oct 2025MediumPX_FCV-274AFCV-274A; IA leak from regulator
25 May 2025LowPX_FCV-274AFCV-274A passing

Recent goods issues

Posting dateQtyOrderOrder type
26 Sept 20261201000028432Corrective
11 Oct 20251201000005255Corrective