POSITIONER,VALVE,SIZE LW189,MONEL
Material 4100048797 · POSITIONER · Plant 1000
BLong-leadReduceSlow-moving
- Material
- 4100048797
- Category
- POSITIONER
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- B (2 of 3 FuncLocs A/B)
- Supplier
- PERMATA INSTRUMEN INTERNASIONAL PT
- Lead time
- 118 d · P80 183 d
- Unit price
- Rp 63.4M
Recommendation
- 1.Forecast 0.5 EA/year: 0.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~118 days; expected demand during lead time 0.2.
- 3.A 98.7% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
- 4.Stock 28 exceeds the level to keep (2) by 26.
- 5.Long lead time: 80% of deliveries took up to 183 days and the fastest seen in its category 40 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Long-leadSingle sourceOpen PO
On hand / on order
28 / 1
next delivery 08 Jan 2027
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
98.7%
stockout risk now 0%
Unit price
Rp 63.4M
PO history
ML early warning: 11% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 287 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 112.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~40 days.
Installed on 3 functional locations
2 with criticality A/B · 3 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_FCV-685 CL-272 OUTLET FLOW | B | 1 | 0 | 0.11 |
| PX_LCV-104 HE-1121A LEVEL CONTROL | B | 1 | 0 | 0.12 |
| PX_TCV-745 PP-1161 TEMP CONTROL | C | 1 | 3 | 0.98 |
Lead time and procurement
Lead time 118 ± 69 days (PO history, 4 PO lines) · on-time 47%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 02 Jun 2026 | PR06 Regular replenishment | 1 | Rp 65.8M | 08 Jan 2027 open | 220 d |
| 24 Mar 2026 | PR03 Regular replenishment | 2 | Rp 65.6M | 17 Jul 2026 | 115 d |
| 29 Oct 2025 | PR06 Regular replenishment | 1 | Rp 61.2M | 17 Dec 2025 | 49 d |
| 27 Jun 2025 | PR06 Regular replenishment | 1 | Rp 61.2M | 02 Dec 2025 | 158 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 08 Sept 2026 | Low | PX_TCV-745 | TCV-745; IA leak from regulator |
| 27 Jul 2026 | Medium | PX_TCV-745 | Install cover plate for MCP cracking |
| 22 Jul 2025 | Low | PX_TCV-745 | Install scaffolding at TCV-745 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 18 Dec 2025 | 1 | 201000035232 | Corrective |