Sparely
DU

POSITIONER,VALVE,SIZE AX247,MONEL

Material 4100048845 · POSITIONER · Plant 1000

CReduceSlow-moving
Material
4100048845
Category
POSITIONER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
SURYA ENERGI JAYA PT
Lead time
85 d · P80 91 d
Unit price
Rp 62.1M

Recommendation

  • 1.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~85 days; expected demand during lead time 0.1.
  • 3.Expected downtime risk is lower than the cost of holding this part, so buying on demand is cheaper.
  • 4.Stock 2 exceeds the level to keep (0) by 2.
Convert to Non StockSingle source
On hand / on order
2 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
–
safety stock 0
Rec. Max
don't stock
order qty 0
Service level
–
stockout risk now 0%
Unit price
Rp 62.1M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 293 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 4.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-939
CONTROL VALVE
C100.11
PX_PCV-1956A
HE-1483A PRESSURE CONTROL
C100.08

Lead time and procurement

Lead time 85 ± 46 days (PO history, 3 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
12 Oct 2025PR03
Regular replenishment
2Rp 60.0M03 Dec 202552 d
29 Sept 2025PR03
Regular replenishment
1Rp 62.1M05 Dec 202567 d
10 Sept 2025PR03
Regular replenishment
2Rp 64.2M26 Dec 2025107 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
12 Dec 20251201000007432Corrective
Sparely