POSITIONER,VALVE,TYPE FF366,A105

Material 4100048928 · POSITIONER · Plant 1000

CReorderHighStockout
Material
4100048928
Category
POSITIONER
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
95 d · P80 166 d
Unit price
Rp 39.9M (est.)

Recommendation

  • 1.Forecast 0.6 EA/year: 0.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.1.
  • 3.A 86.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 1 now.
Proposed purchase requisition
1 EA
Rp 39.9M · order by 01 Oct 2026
Expected arrival ≈ 95 days
Price estimatedLead time estimated
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
86.5%
stockout risk now 13%
Unit price
Rp 39.9M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 229 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 9.8M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~40 days.

Installed on 3 functional locations

0 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-1976A
CONTROL VALVE
C220.96
PX_PCV-1065
PRESSURE CONTROL VALVE
C100.08
PX_LCV-1706A
PP-306A LEVEL CONTROL
S100.12

Lead time and procurement

Lead time 95 ± 64 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
17 Apr 2026LowPX_FCV-1976ALeak from packing
04 Aug 2025MediumPX_FCV-1976AFCV-1976A passing

Recent goods issues

Posting dateQtyOrderOrder type
14 Feb 20261201000012340Corrective