POSITIONER,VALVE,SIZE TL242,CS

Material 4100049073 · POSITIONER · Plant 1000

BLong-leadReorderCriticalStockout
Material
4100049073
Category
POSITIONER
Base unit
EA
MRP type
Non Stock
Criticality
B (2 of 4 FuncLocs A/B)
Supplier
GUNUNG PERKASA NUSANTARA PT
Lead time
100 d · P80 166 d
Unit price
Rp 40.0M

Recommendation

  • 1.Forecast 0.3 EA/year: 0.3 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~100 days; expected demand during lead time 0.1.
  • 3.A 91.9% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 1 now.
  • 5.Long lead time: 80% of deliveries took up to 166 days and the fastest seen in its category 40 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 4 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
1 EA
Rp 40.0M · order by 01 Oct 2026
Expected arrival ≈ 100 days
Long-leadSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
91.9%
stockout risk now 8%
Unit price
Rp 40.0M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 282 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 66.6M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.53% for ~40 days.

Installed on 4 functional locations

2 with criticality A/B · 4 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_LCV-1691
LEVEL CONTROL VALVE
B100.12
PY_FCV-774
HE-589D OUTLET FLOW
B100.11
PX_FCV-1091
PP-167 OUTLET FLOW
C100.11
PX_FCV-750B
HE-1481 OUTLET FLOW
C100.11

Lead time and procurement

Lead time 100 ± 64 days (PO history + category, 2 PO lines) · on-time 35%

PR dateTypeQtyUnit priceDeliveryLead time
01 Jan 2026PR03
Regular replenishment
1Rp 38.9M13 Mar 202671 d
05 Jun 2025PR01
Import / long-lead
2Rp 41.1M29 Oct 2025146 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
23 Dec 20251201000030711Corrective