POSITIONER,VALVE,MODEL BK701,GRAPHITE

Material 4100049230 · POSITIONER · Plant 1000

AReduceSlow-moving
Material
4100049230
Category
POSITIONER
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B)
Supplier
No PO history
Lead time
95 d · P80 166 d
Unit price
Rp 39.9M (est.)

Recommendation

  • 1.Forecast 1.6 EA/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~95 days; expected demand during lead time 0.4.
  • 3.A 98.1% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
  • 4.Stock 6 exceeds the level to keep (4) by 2.
  • 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
6 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
98.1%
stockout risk now 0%
Unit price
Rp 39.9M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 311 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 697.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~40 days.

Installed on 2 functional locations

1 with criticality A/B · 5 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-1256
PP-1570A TEMP CONTROL
A441.40
PX_FCV-1562
CAUSTIC FLOW CONTROL
C110.11

Lead time and procurement

Lead time 95 ± 64 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
30 Jul 2026LowPX_TCV-1256TCV-1256; IA leak from regulator
29 Jul 2026MediumPX_TCV-1256Overhaul TCV-1256
16 Apr 2026MediumPX_TCV-1256Replace lamp as per PM finding
28 May 2025LowPX_FCV-1562Overhaul FCV-1562
05 May 2025MediumPX_TCV-1256Overhaul TCV-1256

Recent goods issues

Posting dateQtyOrderOrder type
24 Nov 20253201000029322Corrective
19 Nov 20251201000016105Corrective