POSITIONER,VALVE,MODEL BK701,GRAPHITE
Material 4100049230 · POSITIONER · Plant 1000
AReduceSlow-moving
- Material
- 4100049230
- Category
- POSITIONER
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (1 of 2 FuncLocs A/B)
- Supplier
- No PO history
- Lead time
- 95 d · P80 166 d
- Unit price
- Rp 39.9M (est.)
Recommendation
- 1.Forecast 1.6 EA/year: 1.6 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~95 days; expected demand during lead time 0.4.
- 3.A 98.1% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 4.
- 4.Stock 6 exceeds the level to keep (4) by 2.
- 5.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
6 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
4
order qty 2
Service level
98.1%
stockout risk now 0%
Unit price
Rp 39.9M
Category + unit estimate
ML early warning: 3% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 311 days ago, 2 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 697.0M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~40 days.
Installed on 2 functional locations
1 with criticality A/B · 5 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_TCV-1256 PP-1570A TEMP CONTROL | A | 4 | 4 | 1.40 |
| PX_FCV-1562 CAUSTIC FLOW CONTROL | C | 1 | 1 | 0.11 |
Lead time and procurement
Lead time 95 ± 64 days (Category estimate, 0 PO lines) · on-time –
No purchase history: price and lead time are estimated from parts of the same category.
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 30 Jul 2026 | Low | PX_TCV-1256 | TCV-1256; IA leak from regulator |
| 29 Jul 2026 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
| 16 Apr 2026 | Medium | PX_TCV-1256 | Replace lamp as per PM finding |
| 28 May 2025 | Low | PX_FCV-1562 | Overhaul FCV-1562 |
| 05 May 2025 | Medium | PX_TCV-1256 | Overhaul TCV-1256 |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 24 Nov 2025 | 3 | 201000029322 | Corrective |
| 19 Nov 2025 | 1 | 201000016105 | Corrective |