SEAT RING,VALVE,TYPE KA462,GRAPHITE
Material 4100050274 · SEAT RING · Plant 1000
ALong-leadReduceSlow-moving
- Material
- 4100050274
- Category
- SEAT RING
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (4 of 7 FuncLocs A/B)
- Supplier
- SINAR SEJAHTERA LESTARI PT
- Lead time
- 106 d · P80 184 d
- Unit price
- Rp 56.9M
Recommendation
- 1.Forecast 0.8 EA/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~106 days; expected demand during lead time 0.2.
- 3.A 99.8% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
- 4.Stock 5 exceeds the level to keep (3) by 2.
- 5.Long lead time: 80% of deliveries took up to 184 days and the fastest seen in its category 65 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 7 FuncLoc(s), 4 of them criticality A/B.
- 7.ML early warning: 37% probability of demand in the next 90 days.
Long-leadML early warningSingle source
On hand / on order
5 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
99.8%
stockout risk now 0%
Unit price
Rp 56.9M
PO history
ML early warning: 37% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 215 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.1B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.
Installed on 7 functional locations
4 with criticality A/B · 9 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_PCV-1887C BY PASS DUCT | A | 1 | 2 | 0.94 |
| PX_LCV-1990 PP-1498C LEVEL CONTROL | A | 1 | 0 | 0.12 |
| PX_TCV-1552B TEMPERATURE CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_TCV-1874A KC-885A TEMP CONTROL | B | 1 | 0 | 0.12 |
| PX_PCV-679 PRESSURE CONTROL VALVE | C | 1 | 2 | 0.51 |
| PX_PCV-1759B BY PASS DUCT | C | 1 | 0 | 0.08 |
| PX_PCV-538 HE-876B PRESSURE CONTROL | S | 3 | 0 | 0.08 |
Lead time and procurement
Lead time 106 ± 58 days (PO history + category, 1 PO lines) · on-time 33%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 30 May 2025 | PR03 Regular replenishment | 2 | Rp 56.9M | 31 Aug 2025 | 93 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 25 Jun 2026 | Medium | PX_PCV-1887C | Install cover plate for MCP cracking |
| 29 Jan 2026 | Medium | PX_PCV-679 | Install cover plate for MCP cracking |
| 16 Jul 2025 | Medium | PX_PCV-1887C | PCV-1887C stuck |
| 04 May 2025 | Low | PX_PCV-679 | PSM25/PCV-679; small leak at packing |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 28 Feb 2026 | 1 | 201000013980 | Corrective |