SEAT RING,VALVE,TYPE AK524,VITON

Material 4100050575 · SEAT RING · Plant 1000

AReduceExcess
Material
4100050575
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
A (3 of 3 FuncLocs A/B)
Supplier
No PO history
Lead time
110 d · P80 184 d
Unit price
Rp 11.3M (est.)

Recommendation

  • 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~110 days; expected demand during lead time 0.4.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 3, order up to 5.
  • 4.Stock 7 exceeds the level to keep (5) by 2.
  • 5.Installed on 3 FuncLoc(s), 3 of them criticality A/B.
Price estimatedLead time estimated
On hand / on order
7 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
3
safety stock 3
Rec. Max
5
order qty 2
Service level
99.9%
stockout risk now 0%
Unit price
Rp 11.3M
Category + unit estimate
ML early warning: 8% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 15 days ago, 5 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 2.0B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.

Installed on 3 functional locations

3 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_TCV-377C
TEMPERATURE CONTROL VALVE
A130.98
PX_LCV-275C
HE-556A LEVEL CONTROL
A120.55
PX_TCV-998
PP-1470A TEMP CONTROL
B141.83

Lead time and procurement

Lead time 110 ± 58 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
24 Aug 2026MediumPX_TCV-998TCV-998 passing
18 Aug 2026LowPX_LCV-275CLCV-275C passing
05 Aug 2026MediumPX_TCV-998Leak from packing
02 Aug 2026MediumPX_TCV-998[MSI-B-26-EHU-261] Permanent repair
13 Jul 2026LowPX_TCV-377CTCV-377C stuck
21 May 2026MediumPX_TCV-377CPainting TCV-377C
27 Aug 2025MediumPX_TCV-998TCV-998; IA leak from regulator
17 Jun 2025LowPX_TCV-377CTCV-377C stuck
03 May 2025MediumPX_LCV-275CLCV-275C passing

Recent goods issues

Posting dateQtyOrderOrder type
16 Sept 20261201000039961Corrective