SEAT RING,VALVE,MODEL GA514,SS304
Material 4100050635 · SEAT RING · Plant 1000
ALong-leadReorderCriticalStockout
- Material
- 4100050635
- Category
- SEAT RING
- Base unit
- EA
- MRP type
- Non Stock
- Criticality
- A (2 of 2 FuncLocs A/B)
- Supplier
- PRIMA INDUSTRI SENTOSA PT
- Lead time
- 136 d · P80 215 d
- Unit price
- Rp 11.8M
Recommendation
- 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
- 2.Lead time ~136 days; expected demand during lead time 0.6.
- 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
- 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
- 5.Long lead time: 80% of deliveries took up to 215 days and the fastest seen in its category 65 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 70.9M · order by 01 Oct 2026
Expected arrival ≈ 136 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 36%
Unit price
Rp 11.8M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 230 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (0 units) excluded from the baseline.
Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.
Installed on 2 functional locations
2 with criticality A/B · 2 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PY_LCV-561 LEVEL CONTROL VALVE | A | 1 | 0 | 0.12 |
| PX_LCV-1098 LEVEL CONTROL VALVE | B | 1 | 0 | 0.12 |
Lead time and procurement
Lead time 136 ± 72 days (PO history, 3 PO lines) · on-time 44%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 09 Nov 2025 | PR04 Regular (other) | 1 | Rp 12.1M | 05 May 2026 | 177 d |
| 15 Aug 2025 | PR05 Project / turnaround | 1 | Rp 11.8M | 12 Apr 2026 | 240 d |
| 09 Aug 2025 | PR06 Regular replenishment | 1 | Rp 11.8M | 16 Oct 2025 | 68 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
No notifications on the equipment this part is installed on.
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 13 Feb 2026 | 1 | 201000013018 | Corrective |
| 02 Oct 2025 | 2 | 201000034184 | Corrective |
| 01 Oct 2025 | 1 | 201000034184 | Corrective |
| 04 Jul 2025 | 1 | 201000005220 | Corrective |