SEAT RING,VALVE,MODEL GA514,SS304

Material 4100050635 · SEAT RING · Plant 1000

ALong-leadReorderCriticalStockout
Material
4100050635
Category
SEAT RING
Base unit
EA
MRP type
Non Stock
Criticality
A (2 of 2 FuncLocs A/B)
Supplier
PRIMA INDUSTRI SENTOSA PT
Lead time
136 d · P80 215 d
Unit price
Rp 11.8M

Recommendation

  • 1.Forecast 1.5 EA/year: 1.5 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~136 days; expected demand during lead time 0.6.
  • 3.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 6.
  • 4.On hand 0 + on order 0 is at or below the reorder point: order 6 now.
  • 5.Long lead time: 80% of deliveries took up to 215 days and the fastest seen in its category 65 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 2 of them criticality A/B.
Proposed purchase requisition
6 EA
Rp 70.9M · order by 01 Oct 2026
Expected arrival ≈ 136 days
Long-leadConvert to Stock ItemSingle source
On hand / on order
0 / 0
no open PO
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
6
order qty 2
Service level
99.9%
stockout risk now 36%
Unit price
Rp 11.8M
PO history
ML early warning: 6% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 230 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Intermittent · 4 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 1.7B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~65 days.

Installed on 2 functional locations

2 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PY_LCV-561
LEVEL CONTROL VALVE
A100.12
PX_LCV-1098
LEVEL CONTROL VALVE
B100.12

Lead time and procurement

Lead time 136 ± 72 days (PO history, 3 PO lines) · on-time 44%

PR dateTypeQtyUnit priceDeliveryLead time
09 Nov 2025PR04
Regular (other)
1Rp 12.1M05 May 2026177 d
15 Aug 2025PR05
Project / turnaround
1Rp 11.8M12 Apr 2026240 d
09 Aug 2025PR06
Regular replenishment
1Rp 11.8M16 Oct 202568 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
13 Feb 20261201000013018Corrective
02 Oct 20252201000034184Corrective
01 Oct 20251201000034184Corrective
04 Jul 20251201000005220Corrective