Sparely
DU

SEAT RING,VALVE,TYPE JM259,NBR

Material 4100050707 · SEAT RING · Plant 1000

CMonitorSlow-moving
Material
4100050707
Category
SEAT RING
Base unit
EA
MRP type
Stock Item
Criticality
C (0 of 2 FuncLocs A/B)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
110 d · P80 184 d
Unit price
Rp 28.9M

Recommendation

  • 1.Forecast 0.4 EA/year: 0.4 unplanned (credibility blend: own history + installed-base prior).
  • 2.Lead time ~110 days; expected demand during lead time 0.1.
  • 3.A 87.5% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
Single sourceOpen PO
On hand / on order
1 / 1
next delivery 17 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
87.5%
stockout risk now 0%
Unit price
Rp 28.9M
PO history
ML early warning: 9% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 194 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 12.2M/yr in expected downtime and emergency buys. A stockout here stops production with probability 0.16% for ~65 days.

Installed on 2 functional locations

0 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_FCV-381
C3 RECYCLE FLOW CONTROL
C120.54
PX_TCV-734A
TEMPERATURE CONTROL VALVE
C100.12

Lead time and procurement

Lead time 110 ± 58 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
18 Aug 2026PR03
Regular replenishment
1Rp 28.3M17 Nov 2026
open
91 d
06 Mar 2026PR05
Project / turnaround
2Rp 29.5M11 Jul 2026127 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
18 Mar 2026MediumPX_FCV-381FCV-381; IA leak from regulator
26 May 2025HighPX_FCV-381FCV-381; valve hunting

Recent goods issues

Posting dateQtyOrderOrder type
21 Mar 20261201000018631Corrective