SOLENOID VALVE,SIZE LR365,PTFE
Material 4100051941 · SOLENOID VALVE · Plant 1000
ASafety-criticalLong-leadMonitorHealthy
- Material
- 4100051941
- Category
- SOLENOID VALVE
- Base unit
- EA
- MRP type
- Stock Item
- Criticality
- A (14 of 29 FuncLocs A/B, 21 safety/shutdown valve)
- Supplier
- BUANA INDUSTRI LESTARI PT
- Lead time
- 51 d · P80 97 d
- Unit price
- Rp 6.6M
Recommendation
- 1.Safety-critical element: installed on 21 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
- 2.Forecast 4.7 EA/year: 4.7 unplanned (credibility blend: own history + installed-base prior).
- 3.Lead time ~51 days; expected demand during lead time 0.7.
- 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 4, order up to 8.
- 5.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 35 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
- 6.Installed on 29 FuncLoc(s), 14 of them criticality A/B.
- 7.ML early warning: 50% probability of demand in the next 90 days.
Safety-critical (SCE)Long-leadML early warningSingle source
On hand / on order
6 / 0
no open PO
Today Min / Max
1 / 3
static parameters in BoM
Rec. Min (reorder point)
4
safety stock 4
Rec. Max
8
order qty 4
Service level
99.9%
stockout risk now 0%
Unit price
Rp 6.6M
PO history
ML early warning: 50% probability this part is needed in the next 90 days (above the 30% warning threshold). Inputs: 1 issue days in the last 180 days, last issue 87 days ago, 6 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.
Consumption history and 12-month forecast
Units per month. Turnaround issues (1 units) excluded from the baseline.
Demand pattern Intermittent · 5 issue days · method: Credibility blend: own history + installed-base prior.
Cost of each service level
Annual holding vs downtime-risk cost for this part
Not stocking at all would cost Rp 3.5B/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~35 days.
Installed on 29 functional locations
14 with criticality A/B · 41 units installed
| FuncLoc | Crit. | Installed | Notifications | Failures / yr |
|---|---|---|---|---|
| PX_KT-856A TURBINE FOR KC-856A | A | 3 | 7 | 2.81 |
| PX_KT-397A TURBINE FOR KC-397A | A | 1 | 5 | 2.81 |
| PX_KT-460B TURBINE FOR KC-460B | A | 4 | 2 | 1.96 |
| PX_KT-513 TURBINE FOR KC-513 | A | 1 | 2 | 1.53 |
| PX_SDV-121 ON-OFF VALVE | A | 1 | 0 | 0.06 |
| PX_SDV-124 DILUTION STEAM ISOLATION | A | 2 | 0 | 0.06 |
| PX_SDV-1862 ON-OFF VALVE | A | 1 | 0 | 0.06 |
| PX_SDV-584 REFLUX ISOLATION | A | 1 | 0 | 0.06 |
| PX_SDV-626B VD-534A SHUTDOWN VALVE | A | 1 | 0 | 0.06 |
| PY_SDV-1845 CAUSTIC ISOLATION | A | 1 | 0 | 0.06 |
| PX_SDV-1540 PP-1250 SHUTDOWN VALVE | B | 1 | 0 | 0.06 |
| PX_SDV-1771 ON-OFF VALVE | B | 1 | 0 | 0.06 |
Lead time and procurement
Lead time 51 ± 19 days (PO history + category, 2 PO lines) · on-time 38%
| PR date | Type | Qty | Unit price | Delivery | Lead time |
|---|---|---|---|---|---|
| 27 Sept 2025 | PR03 Regular replenishment | 2 | Rp 6.6M | 11 Dec 2025 | 75 d |
| 12 Aug 2025 | PR06 Regular replenishment | 2 | Rp 6.6M | 18 Sept 2025 | 37 d |
Planned maintenance demand (next 12 months)
No part-consuming maintenance job uses this part in the next 12 months.
Recent notifications on its equipment
| Date | Priority | FuncLoc | Description |
|---|---|---|---|
| 19 Sept 2026 | High | PX_KT-383A | [MSI-B-26-CWK-358] Permanent repair |
| 18 Sept 2026 | Medium | PX_KT-202 | Repair insulation KT-202 |
| 16 Sept 2026 | Medium | PX_KT-383A | Install scaffolding at KT-383A |
| 02 Sept 2026 | Low | PX_KT-383A | Replace lamp as per PM finding |
| 23 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 19 Aug 2026 | Medium | PX_KT-383A | Follow up after steam upset KT-383A |
| 20 Jul 2026 | Low | PX_KT-856A | Follow up after steam upset KT-856A |
| 26 Jun 2026 | Medium | PX_SDV-398A | SDV-398A fail to close |
| 26 May 2026 | Low | PX_KT-397A | Follow up after steam upset KT-397A |
| 24 May 2026 | High | PX_KT-383A | KT-383A steam leak at gland |
Recent goods issues
| Posting date | Qty | Order | Order type |
|---|---|---|---|
| 08 Sept 2026 | 1 | 203000039516 | Turnaround |
| 06 Jul 2026 | 1 | 201000030618 | Corrective |
| 25 Dec 2025 | 1 | 201000038819 | Corrective |
| 15 Oct 2025 | 1 | 201000026389 | Corrective |
| 30 Sept 2025 | 1 | 204000021212 | Preventive |
| 23 Sept 2025 | 1 | 201000033203 | Corrective |