SOLENOID VALVE,TYPE LZ682,GRAPHITE

Material 4100052337 · SOLENOID VALVE · Plant 1000

ASafety-criticalLong-leadMonitorSlow-moving
Material
4100052337
Category
SOLENOID VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (1 of 2 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
BUANA INDUSTRI LESTARI PT
Lead time
59 d · P80 97 d
Unit price
Rp 4.6M

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.8 EA/year: 0.8 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~59 days; expected demand during lead time 0.1.
  • 4.A 100.0% service level gives the lowest holding + downtime-risk cost: reorder at 2, order up to 3.
  • 5.Long lead time: 80% of deliveries took up to 97 days and the fastest seen in its category 35 days, from a single supplier. Emergency buying cannot prevent downtime: plan ahead or hold as a capital spare.
  • 6.Installed on 2 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Long-leadSingle sourceOpen PO
On hand / on order
2 / 1
next delivery 21 Nov 2026
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
2
safety stock 2
Rec. Max
3
order qty 1
Service level
100.0%
stockout risk now 0%
Unit price
Rp 4.6M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 197 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 2 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 580.7M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~35 days.

Installed on 2 functional locations

1 with criticality A/B · 2 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_SDV-1320
KC-669 SHUTDOWN VALVE
A100.06
PX_SDV-151
ON-OFF VALVE
S100.06

Lead time and procurement

Lead time 59 ± 19 days (PO history + category, 2 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
03 Aug 2026PR01
Import / long-lead
1Rp 4.5M21 Nov 2026
open
110 d
09 Feb 2026PR03
Regular replenishment
1Rp 4.6M23 Mar 202642 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
18 Mar 20261201000022030Corrective
17 Mar 20261201000022030Corrective