SOLENOID VALVE,SIZE KJ979,NBR

Material 4100052493 · SOLENOID VALVE · Plant 1000

ASafety-criticalMaintainCritical insurance spare
Material
4100052493
Category
SOLENOID VALVE
Base unit
EA
MRP type
Stock Item
Criticality
A (2 of 3 FuncLocs A/B, 2 safety/shutdown valve)
Supplier
No PO history
Lead time
48 d · P80 97 d
Unit price
Rp 11.3M (est.)

Recommendation

  • 1.Safety-critical element: installed on 2 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.1 EA/year: 0.1 unplanned (installed-base failure prior (no history)).
  • 3.Lead time ~48 days; expected demand during lead time 0.0.
  • 4.A 98.4% service level gives the lowest holding + downtime-risk cost: reorder at 0, order up to 1.
  • 5.No issue in 17 months, but it protects critical equipment: keep it.
  • 6.Installed on 3 FuncLoc(s), 2 of them criticality A/B.
Safety-critical (SCE)Price estimatedLead time estimated
On hand / on order
1 / 0
no open PO
Today Min / Max
1 / 2
static parameters in BoM
Rec. Min (reorder point)
0
safety stock 0
Rec. Max
1
order qty 1
Service level
98.4%
stockout risk now 0%
Unit price
Rp 11.3M
Category + unit estimate
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue never, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 0 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern No demand · 0 issue days · method: Installed-base failure prior (no history).

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 88.5M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~35 days.

Installed on 3 functional locations

2 with criticality A/B · 3 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_KT-419A
TURBINE FOR KC-419A
A162.81
PY_SDV-1973A
VD-694 SHUTDOWN VALVE
A110.06
PX_SDV-1914
SPENT CAUSTIC ISOLATION
S100.06

Lead time and procurement

Lead time 48 ± 19 days (Category estimate, 0 PO lines) · on-time –

No purchase history: price and lead time are estimated from parts of the same category.

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

DatePriorityFuncLocDescription
03 Apr 2026MediumPX_KT-419AKT-419A steam leak at gland
17 Mar 2026MediumPX_KT-419AInstall cover plate for MCP cracking
20 Nov 2025MediumPX_KT-419ALeak from packing
10 Nov 2025MediumPX_KT-419APainting KT-419A
03 Sept 2025MediumPX_KT-419AFollow up after steam upset KT-419A
30 May 2025LowPY_SDV-1973ASDV-1973A limit switch faulty
15 May 2025LowPX_KT-419APSM25/Leak from packing

Recent goods issues

Never issued in the 17-month history.