Sparely
DU

SOLENOID VALVE,MODEL YM973,NBR

Material 4100052914 · SOLENOID VALVE · Plant 1000

ASafety-criticalReduceSlow-moving
Material
4100052914
Category
SOLENOID VALVE
Base unit
EA
MRP type
Non Stock
Criticality
A (1 of 1 FuncLocs A/B, 1 safety/shutdown valve)
Supplier
KARYA ENERGI SENTOSA PT
Lead time
61 d · P80 87 d
Unit price
Rp 6.1M

Recommendation

  • 1.Safety-critical element: installed on 1 safety or shutdown valve location(s). Downtime risk is costed as class A and at least 1 spare is always kept; any reduction needs Management sign-off.
  • 2.Forecast 0.2 EA/year: 0.2 unplanned (credibility blend: own history + installed-base prior).
  • 3.Lead time ~61 days; expected demand during lead time 0.0.
  • 4.A 99.9% service level gives the lowest holding + downtime-risk cost: reorder at 1, order up to 2.
  • 5.Stock 24 exceeds the level to keep (2) by 22.
  • 6.Installed on 1 FuncLoc(s), 1 of them criticality A/B.
Safety-critical (SCE)Single sourceOpen PO
On hand / on order
24 / 1
next delivery 07 Nov 2026
Today Min / Max
0 / 0
static parameters in BoM
Rec. Min (reorder point)
1
safety stock 1
Rec. Max
2
order qty 1
Service level
99.9%
stockout risk now 0%
Unit price
Rp 6.1M
PO history
ML early warning: 5% probability this part is needed in the next 90 days (below the 30% warning threshold). Inputs: 0 issue days in the last 180 days, last issue 281 days ago, 0 failure notifications on its equipment in 90 days, 0 planned jobs in 90 days, 1 PRs in 180 days.

Consumption history and 12-month forecast

Units per month. Turnaround issues (0 units) excluded from the baseline.

Demand pattern Single issue · 1 issue days · method: Credibility blend: own history + installed-base prior.

Cost of each service level

Annual holding vs downtime-risk cost for this part

Not stocking at all would cost Rp 147.9M/yr in expected downtime and emergency buys. A stockout here stops production with probability 1.07% for ~35 days.

Installed on 1 functional locations

1 with criticality A/B · 1 units installed

FuncLocCrit.InstalledNotificationsFailures / yr
PX_SDV-848B
VD-664B SHUTDOWN VALVE
A100.06

Lead time and procurement

Lead time 61 ± 30 days (PO history, 4 PO lines) · on-time 38%

PR dateTypeQtyUnit priceDeliveryLead time
22 Sept 2026PR06
Regular replenishment
1Rp 6.0M07 Nov 2026
open
46 d
15 Mar 2026PR06
Regular replenishment
2Rp 6.2M19 Jul 2026126 d
24 Jan 2026PR06
Regular replenishment
2Rp 6.2M26 Mar 202661 d
20 Sept 2025PR06
Regular replenishment
1Rp 5.8M09 Nov 202550 d

Planned maintenance demand (next 12 months)

No part-consuming maintenance job uses this part in the next 12 months.

Recent notifications on its equipment

No notifications on the equipment this part is installed on.

Recent goods issues

Posting dateQtyOrderOrder type
24 Dec 20251201000036901Corrective